Cost and timescales
Extras

The new foot and cycle bridge has cost £3million.

The funds came from developers working in the area and from Communities and Local Government's Growth Area Fund.

Possible timescales


December
2007

The main span of the bridge was lifted into place. 

Consultation on the traffic management measures on Riverside ended.


January 2008

Painting and finishing works on site. 

Construction of the footpath from the bridge to St Andrew’s Road. 

City and County Councillors vote to keep the road closure on Riverside as a permanent feature.

June
2008

The new bridge opened to the public on Thursday, 5 June 2008 at approximately midday.

External links

Central Government's Communities and Local Government

Contacts

Riverside Bridge project team

Cambridgeshire County Council
ET1017
Castle Court
Shire Hall
Cambridge
CB3 0AP

Tel:01223 717759
Fax:   01223 717752
Contact us:  Email us 
 


©Cambridgeshire County Council 2008 : Shire Hall, Castle Hill, Cambridge, CB3 0AP : 0845 045 5200 : Privacy Statement