EN
Accessibility Options

Before surface treatments start

During January, February, March and April, patching works will take place on some of the roads selected for surface treatments. You may see workmen patching parts of the road only. This is to repair and seal the existing road surface so the road will be ready for surface treatment later in the year.

Surface treatments scheduled for 2019

All the work dates listed are indicative only. These treatments can only be laid in good weather and work will need to be postponed if it is wet or raining. Any postponements will then cause knock on delays to street works later in the program. Please keep an eye out for local signage, check our upcoming roadwork information on our roadworks and traffic webpage, or follow us on Twitter - Cambs_Traffic for the most up to date information on where we will be working.

Micro Asphalt

Roads chosen for Micro Asphalt treatment can be found below listed by district. Road closures will be in place while the works are underway.

All works in Cambridge City will be taking place between 9:30am and 3:30pm. 

Micro Asphalt treatment
StreetTown/VillageEstimated date of the worksDuration
Howgate Road Impington Early April 1 day
St Catherine's Square Impington Early April 1 day
St Catherine's Rd Impington Early April 3 days
Walnut Tree Way Impington Early April 1 day
Sunset Square Impington Early April 2 days
Jedburgh Close Kings Hedges Early April 2 days
Callander Close Kings Hedges Early April 1 day
Banff Close Kings Hedges Early April 1 day
Moncrief Close Kings Hedges Early April 2 days
Caledon Way Kings Hedges Early April 2 days
Buchan Street Kings Hedges Early April 2 days
Augustus Close Kings Hedges Mid April 1 day
Hercules Close Kings Hedges Mid April 1 day
Minerva Way Kings Hedges Mid April 1 day
Enniskillen Road East Chesterton Mid April 2 days
Wycliffe Road Romsey Mid April 1 day
Teynham Close Coleridge Mid April 1 day
Robert May Close Coleridge Mid April 1 day
Britten Place Coleridge Mid April 1 day
Trevone Place Coleridge Mid April 1 day
Tiverton Way Coleridge Mid April 2 days
Ancaster Way Coleridge Mid April 1 day
Corrie Road Coleridge Mid April 2 days
Bancroft Close Coleridge Mid April 1 day
Sterne Close Coleridge Mid April 1 day
Fanshawe Road Coleridge Mid April 2 days
Topcliffe Way Queen Ediths Mid April 2 days
Maners Way Queen Ediths Mid April 1 day
Kinnaird Way Queen Ediths Mid April 3 days
Rotherwick Way Queen Ediths End of April 1 day
Nightingale Avenue Queen Ediths End of April 3 days
Bowers Croft Queen Ediths End of April 2 days
Field Way Queen Ediths End of April 2 days
Colville Road (remedial works) Cherry Hinton Early June 2 days

All works in South Cambridgeshire will be taking place between 8am and 6pm unless specified otherwise below.

Micro Asphalt treatment
StreetTown/VillageEstimated date of the worksDuration
Greenside Close Swavesey End of April 1 day
Nether Grove Longstanton End of April 2 days
Clive Hall Drive Longstanton End of April 1 day
Priors Close Histon End of April 1 day
Ambrose Way Impington End of April 2 days
Faulkner Close Milton End of April 1 day
The Elms Milton End of April 2 days
The Sycamores Milton End of April/Early May 4 days
Wheatsheaf Way Linton Early May  2 days (9:30am to 3:30pm)
Dolphin Close Linton Early/Mid May 2 days (9:30am to 3:30pm)
Balingdon Lane Linton Early/Mid May 1 day
Brinkman Road Linton Early/Mid May 2 day
Pembroke Lane Linton Early/Mid May 1 day
Hollybush Way Linton Early/Mid May 2 days
Bawtree Crescent Linton Early/Mid May 1 day
Park Road Sawston Early/Mid May 2 days
Maple Ave Sawston Mid May 2 days
Rowan Ave Sawston Mid May 1 day
Hawthorn Ave Sawston Mid May 1 day
Mortlock Close Melbourn Mid May  1 day (9:30am to 3:30pm)
Church View (remedial works) Oakington Early June 2 days

All works in Fenland and East Cambridgeshire will be taking place between 8am and 6pm unless specified otherwise below.

Micro Asphalt treatment
StreetTown/VillageEstimated date of the worksDuration
Goddard Crescent Wisbech End of April 1 day
Grosvenor Road Wisbech End of April 2 days
Fenland Road Wisbech End of April 3 days
Robin Mews Wisbech End of April 1 day
Redwing Drive Wisbech End of April 1 day
Kingfisher Drive Wisbech End of April 1 day
Kestrel Drive Wisbech End of April 1 day
Heron Road Wisbech End of April 2 days
Claygate Whittlesey End of April 1 day
Smiths Drive March End of April 2 days
Meadow Drive March End of April/Early May 1 day
Collingwood Avenue March End of April/Early May 2 days
Morton Avenue March End of April/Early May 2 days
Ferry Way Littleport End of April/Early May 1 day
Dalton Way Ely Early May 2 days
John Amner Close Ely Early May 2 days
Bellairs Sutton Early May 2 days (9:30am to 3:30pm)
Wichford Road (remedial works) Ely Early June 1 day
Northwold (remedial works) Ely Early June 1 day
Arundell (remedial works) Ely Early June 1 day
Fleetwood (remedial works) Ely Early June 1 day

Gripfibre treatment
StreetTown/VillageEstimated date of worksDuration
Lerowe Road Wisbech Late May 2 days
B1101 March Road Friday Bridge Late May 1 day
Ely Road Sutton Late May 2 days
Mildenhall Road Fordham Late May 3 days

All works in Huntingdonshire will be taking place between 8am and 6pm unless specified otherwise below.

Micro Asphalt treatment
StreetTown/VillageEstimated date of the worksDuration
Knowles Ave Warboys Early May 2 days
Garner Ave Warboys Early May 1 day
Bottels Road Warboys Early May 2 days
Falcon Drive Hartford Mid May 2 days
Tawny Crescent Hartford Mid May 1 day
Owl Way Hartford Mid May 3 days
Asplin Ave Needingworth Late May 1 day
Dales Way Needingworth Late May 1 day
Ravenscourt Needingworth Late May 1 day
Townsend Road Needingworth Late May 2 days
Millfields
(remedial works)
Ramsey Early June 1 day
Morland Way (remedial works) St Ives Early June 1 day

Surface Dressing

Roads chosen for surface dressing treatment can be found below. Road closures will be in place while the works are underway.

Street name Town / village Estimated date of works
Graveley Road Offord Darcy 02/07/2019
Barrington Road Orwell 03/07/2019
B1042 Lower Road Croydon 03/07/2019 - 04/07/2019
B1368 Barley Road Great Chishall 05/07/2019
A1307 Cambridge Road Little Abington 08/07/2019
B1042 Frogge Street Ickleton 08/07/2019
B1042 Hill Farm Road Whittlesford 09/07/2019
Whittlesford Road Little Shelford 09/07/2019 - 10/07/2019
B1042 Chishall Grange Road Thriplow 10/07/2019 - 11/07/2019
B1061 Bradley Road Burrough Green 11/07/2019
East Fen Drove Soham 12/07/2019
A1123 Newmarket Road Stretham 12/07/2019 
A10 Downham Road Ely 13/07/2019
Ely Road Chettisham 14/07/2019
B1049 Twenty Pence Road Cottenham 15/07/2019 - 16/07/2019
Ely Way Haddenham 16/07/2019
B1102 Mildenhall Road Fordham 16/07/2019 - 17/07/2019
Waterside Isleham 17/07/2019
Marsh Lane Hemingford Grey 17/07/2019
B1086 St Ives Road Somersham 17/07/2019 - 18/07/2019
Bury Road Upwood 18/07/2019
Ugg Mere Ct Road Ramsey Heights 18/07/2019 - 19/07/2019
Twenty Foot Road March 19/07/2019 - 22/07/2019
Main Road Parson Drove 22/07/2019 
High Road Newton-in-the-Isle 22/07/2019
Mill Lane Newton-in-the-Isle 22/07/2019 - 23/07/2019
A1101 Sutton Road Four Gotes 23/07/2019 - 24/07/2019
Hamerton Road Alconbury Weston 24/07/2019 - 25/07/2019
Caldecote Road Stilton 25/07/2019
Clopton Road Old Weston 25/07/2019
High Street Brington 25/07/2019 - 26/07/2019
Molesworth Road Old Weston 26/07/2019 - 27/07/2019
Stow Road Kimbolton 27/07/2019
High Street Tilbrook 27/07/2019 - 28/07/2019

What to expect if your road is being treated

Advanced warning signs will be placed on the roads affected at least seven days of the work's start date.  For our annual surface treatments, residents will receive a leaflet from us informing them of what works are taking place on their street. For our other roadworks, properties directly impacted by works will receive a letter detailing the exact times of the works. 

While the work is happening, we ask all residents to not park their car on the road that is being worked on. We will need access to the whole road at all times. 

For surface treatment works, roads may need to close. In those cases, a diversion route will be signed (unless it's a cul-de-sac road). If you live on a road where works are taking place and your access is blocked, please speak to staff on site. Access for residents of the road may be allowed, however you may need to wait until it’s safe to do so or you may be required to use a different route. Anyone who can avoid the road should do so while works are underway.

Diversion routes 

For diversion routes, we use the same or higher category of road as the road that is closed. This is to ensure the diversion route can cope with all the same types of traffic as the closed road. In some rural locations, a lesser category route may be agreed to when there is no other alternative.

 

Only our approved diversion route will be sign posted. However there are often locally known roads which vehicles can choose to use instead. We have no powers to prevent highway users using these alternative routes.

Please take care when driving on the newly laid surface as there is likely to be some loose chippings. Until we have returned to the site to sweep away loose chippings, please follow temporary speed limit signage.

See below our information leaflets for residents affected by the works:

Highways Leaflet Micro-Asphalt

Size: 1.04 MB File format: pdf

Highways Leaflet Surface Dressing

Size: 2.22 MB File format: pdf

Treatment types

Surface treatments across Cambridgeshire consist of a number of different varieties, all are designed to seal the surface, add texture and conformity and extend the life expectancy of the road.

The varieties we use are surface dressing, Micro Asphalt, Footway Slurry Seal, and Retread.

Surface Dressing

Surface dressing can be disruptive and may require the road to be closed temporarily. Once completed, it can receive traffic immediately provided speeds stay below 20 miles per hour.

Surface dressing is very weather dependent and cannot happen if it's too hot, too cold or wet. This means the work schedule can change at short notice. The season for this treatment generally runs from April to September.

Surface dressing is a robust and cost effective method of maintaining our roads. It is a preventative treatment so will not repair roads that have structural issues, and will not alter the shape of a road. Some roads with minor defects can be treated, following planned preparation work in advance.

The road surface is sprayed with a coating of liquid bitumen. Stone chippings are then rolled onto the road to form a water resistant, protective layer.  

Surface dressing

Video of our Etnyre machine in action

The object of surface dressing is to prevent potholes and extend the life of a road for up to 10 years. It will give the road added texture, improving skid resistance, and give conformity to a heavily scarred surface.

Micro Asphalt

Micro Asphalt can be laid in temperatures as low as 5 degrees, which means the laying season can extend  from early March to mid-November. The process can only be laid in dry weather so the work schedule may change if it's wet. It is also normally a requirement that the road is closed whilst the work is carried out.

A more enhanced variant of Micro Asphalt, called Grip Fibre may be considered for use on busier roads as it is stronger. The season for laying this runs from May to August.

This surface treatment is best used on roads which show early stages of wear and tear. It is laid over the top of an existing road surface. The effect of this treatment is to protect and seal the surface of the road thus preventing further deterioration and extending the life of the road. It also assists road safety by improving skid resistance.

Before treatment, the road is swept to remove any loose material and any ironwork is masked with tape. Following the treatment the masking is removed and if needed, the ironwork will be adjusted in the near future. Traffic can use the road 20 minutes after the material is laid but a 20 miles per hour speed limit will be in place.

The road will normally shed some stone over the first few weeks after treatment. This is typical and will be subject to sweeping as required. The new surface is very black and does appear slightly messy shortly after it is laid. This is normal and usually settles down after a number of weeks.

Footway Slurry Seal

A low cost preventative maintenance process, designed to seal in the surface of a structurally sound footway and prolong its life.

It is not suitable for a footway that is not in a structurally acceptable condition and does not add strength. It will fill minor depressions and voids and provide a more even surface, improving the quality of slip resistance.

Slurry is a mixture of bitumen emulsion, aggregate and water spread over the existing footway and brushed to give a textured finish. It may be necessary to prepare the existing surface by cleaning, weed spray, minimal patching and raising ironwork.

Although a quick process, the surface will remain wet for several hours following treatment and the treated footway will need to remain closed until it dries. As with all thin coat surfacing, the process is weather and temperature dependent.

Retread

A process where the existing surface is planed up, re-graded and re-profiled on site. It is then compacted down and receives either a surface treatment or a tarmac over lay. The road will require to be closed throughout the process, and depending on the size of the site, this may be for several days. It is suitable for roads that have deteriorated further, but do not have a particularly heavy traffic flow.

Did you find this information useful?

Loader