Starting September 2018, Cambridgeshire County Council will carry out carriageway resurfacing at 17 locations across the county. View information for local residents.

The roads selected as part of this package are suffering from surface deterioration, cracking or joint failure which is leading to increasingly frequent potholes. Many are at the end of their usable life. Most of these works will require a full or overnight road closure. 

Work schedule

As with all our resurfacing works, the timings and dates for these works are weather dependent and can change at short notice. Please keep an eye on this webpage for schedule changes. You can also follow our twitter page @Cambs_Traffic for updates on the day or keep an eye on local signage for more information.

List of roads to be treated

Huntingdonshire

Road nameStart dateWork durationTraffic managementDiversion map and work plan
Mill Road Great Gidding 17 September 2018 Five days Work complete Diversion map
Work plan
C89 Hod Fen Drove 27 September 2018 39 days Work complete Diversion map
Work plan
B1086 Somersham 27 October 2018 Three days Work complete Diversion map
Work plan
B1050 London/ Chatteris Road 5 November 2018 30 days 24 hour road closure Diversion map
Work plan

East Cambridgeshire

Road nameStart dateWork durationTraffic managementDiversion map and work plan
Lynn Road, Ely 10 October 2018 Eight days Work complete

Diversion map
Work plan
Public notice

A10 Littleport Bypass 08 October 2018 Nine days Work complete Diversion map
Work plan
A142 Witcham Toll 24 October 2018 10 days Work complete Diversion map
Work plan
A10 Lynn Road, Littleport 24 October 2018 11 days Work complete Diversion map
Work plan
A10 Little Thetford 19 November 2018 Six days Road closure from 8:30pm to 5:30am. 40mph limit in place during day. Diversion map

Long North Fen Drove Sutton 3 December 2018 14 days 24 hour road closure Diversion route

South Cambridgeshire and Cambridge City

Road nameStart dateWork durationTraffic managementDiversion map and work plan
A1307 Haverhill  Road 17 September 2018 Seven days Work complete Work plan
Walnut Tree Avenue, Cambridge 24 September 2018 Two days Work complete Work plan
A603 Barton Roundabout and J12 exit on M11 (Replacing vehicle barrier) 8 October 2018 45 days One lane closed from 9:30am to 3:30pm. 40mph limit during evening/night.
A1307 Horseheath Bypass  24 September 2018 Five days Work complete Work plan
Fen Road, Milton 26 September 2018 Three days Road closure from 7:30am to 6:30pm.  Work plan

A1307 Cambridge Road (Westbound)

1 October 2018 Four days Work complete Work plan

C259 Haslingfield Rd, Barton

29 October 2018 5 days Work complete Diversion route

A1303
Stow cum Quy

23 November 2018 1 day Road closure from 8pm to 6am Diversion route Work plan
Cambridge Road, Milton 10 November 2018 Three days Work complete

Lane closure plan Milton roundabout

Diversion map Phase 1

Diversion map Phase 2

Work plan

A1303 Madingley Road 3 December 2018 Three days Road closure from 9:30pm to 5:30am. 40mph limit during the day. Diversion map
Work plan
A603 Barton roundabout (Part Two) January 2019 January 2019 Road closure from 8pm to 6am. 40mph limit during the day. Diversion map
Work plan

What will the work involve?

For this work, we will be using innovative techniques never tried before in Cambridgeshire to improve the road condition, minimise travel disruption and reduce the need for future road maintenance. By using our own material created specially for these roads and recycling old material, we are working in a more environmentally sustainable way while reducing our project costs.

To find out more about what will be happening on each road and what we're doing differently, please see the below documents.

East Cambridgeshire schemes brief

Size: 93.60 KB File format: pdf

Huntingdonshire schemes brief

Size: 90.98 KB File format: pdf

South Cambridgeshire and City schemes brief

Size: 103.02 KB File format: pdf

What we're doing differently 2018/2019

Size: 295.01 KB File format: pdf

How will local residents be affected? 

I live on one of the roads that will be closed, how can I get access during the road closure? Our contractors will allow you access to and from your property. Properties whose access is directly impacted will receive a letter from us shortly before the works start. This letter will include a resident pass. Please show this pass to staff on site at the point of closure so they can allow you through. 

During the work, we ask all residents to not park their car on the road that is due to be resurfaced as we will need to resurface the full width of the road.

I regularly commute using a road that will be closed, how can I get access? Commuters will not be allowed to pass through while a road is closed so please follow the signed diversion route or use alternative roads.

For some of the more busy routes, we will not close the road. For safety, all drivers will need to wait to be escorted through the works by a convoy vehicle. This may result in significant delays to your journey so we recommend commuters avoid the road if at all possible while the works are underway.

Will there be a lot of noise during these works? Unfortunately, some noise will be unavoidable. We will be monitoring the level of noise on site however if you have specific concerns about noise, please contact us below.

Who can I contact for more information about works on my road? These works are all being carried out by our contractor Tarmac. If you have a specific concern, please contact us at  [email protected] or call the on site team on 074 83395881