Read our Whittlesey traffic update for the latest information.
Update: 25 November 2024
The westbound carriageway, heading to Peterborough, on the Ralph Butcher Causeway at King’s Dyke is temporarily closed for safety reasons. The lane that is temporarily closed using two-way traffic lights will unfortunately remain closed while the contractor Jones Brothers carry out further surveys and tests of the carriageway and the embankment to understand why the cracks in the road have appeared.
Only once the contractor has identified the cause of the cracking and made the necessary repairs can the temporary traffic lights be removed and the traffic lane be re-opened.
Unfortunately, due to the nature of the monitoring and testing we are unable at this point to provide any programme for when the lane can be reopened, however it will be reopened as soon as it is safe to do so. We’d like to thank people for their patience during this time, and further information will be provided in due course.
Project background
The 2001 Local Transport Plan identified that the King's Dyke level crossing in Whittlesey was in need of replacement.
A new scheme is required to allow for housing and job growth within Whittlesey, as well as reducing journey times for those who use the route.
In peak periods, the level crossing barrier can be down for between 12 and 23 minutes per hour, resulting in significant delays to traffic. Future plans by the rail industry to increase the number of trains travelling along the route are set to further increase traffic delays.
We conducted a public consultation in 2014 on proposals to replace the level crossing. 95% of respondents supported the scheme.
58% of respondents, as well as some local businesses and Whittlesey Town Council, supported a route which would bypass the existing level crossing to the south. It involves creating two new roundabouts at Funthams Lane and the brickworks access road.
The scheme requires significant earthworks, ground stabilisation and construction of a bridge over the railway line, which can only close for very short periods of time.
A number of improvements and alterations to the highway network must be made to build this scheme. The work requires a Side Roads Order, which is a statutory order authorising the council to make alterations to the highway network. An order has been approved by the Secretary of State for Transport.
Current stage of project
There will be no drawbacks now a new bridge over King’s Dyke Level Crossing has opened today, Monday 11 July.
Regular delays caused by passing trains will now be a thing of the past thanks to the speedy progress made by Jones Bros Civil Engineering UK. After hitting this major milestone, the civil engineering contractor will now focus its attention on the existing A605 as work enters the final stretch of the £32 million scheme.
This includes completing the eastern roundabout tie-in, which Jones Bros can only action when traffic is using the new road. There will be approximately three weeks of two-way traffic lights, operating 24 hours a day while this work is completed.
Further works include the construction of an embankment near Forterra, works at Funtham’s Lane, landscaping, and the closure and removal of the level crossing.
Jones Bros was appointed by Cambridgeshire County Council and began on site in July 2020 with works expected to continue until the end of this year. However, commuters will notice significantly reduced travel times and disruption after the eastern tie-in works are completed, with no further traffic management planned on the new road as part of the scheme.
Timeline of project so far
Project funding
The current approved scheme budget of £32 million is made up of funding from:
- Cambridgeshire County Council
- Growth Deal funding approved by the former Local Enterprise Partnership (LEP)
- Cambridgeshire and Peterborough Combined Authority's (CPCA) Transforming Cities Fund
There is a separate £1.5 million Covid-19 contingency budget to fund any additional costs directly associated with the project caused by the impact of Coronavirus.
Frequently asked questions
Newsletter
Jones Bros produce a quarterly newsletter about the King's Dyke level crossing project. We publish the latest edition.
Documents
Documents relating to the scheme are available to view below, including Side Roads Orders, options assessments and feasibility reports.
Contact us
For more information about the scheme, please email Transport.Delivery@cambridgeshire.gov.uk or telephone 01223 699 069.
We are aware that not all the documents on this page are in an accessible format at the moment. If you would like any of the resources in an accessible format please contact infoservices@cambridgeshire.gov.uk.