We maintain over 4,600 kilometres of road network across the county on behalf of our communities. This includes: 

  • 532 km of A-road network
  • 578 km of B-road network
  • 3,498 km of C and Unclassified Road network
  • In 2023, 5.1 billion vehicle miles were travelled in Cambridgeshire, an increase of over half a billion vehicle miles in ten years.
  • Over 40% of our network is built over peat soil which present unique challenges as it is structurally weak.
Road with two lanes with grass and bushes on both sides

The information here provides details on the planned repairs to roads that we will be undertaking throughout 2024 and 2025 across the county.

The scale and type of work will vary depending on the individual scheme and the repair being undertaken.

Most work will be delivered under a full road closure. This will cause disruption to the road network whilst we are on site. We will keep disruption to a minimum and we appreciate your cooperation during these critical works.

As well as the large-scale work on roads, planned in advance, we also continually do reactive road repairs across the whole county. These include pothole repairs and patching work, which is carried out on defects that we spot through routine inspection or if an issue has been reported by a member of the public. This helps keep the highways network running smoothly.

Planned work by district for 2024-2025

Updates are provided monthly by officers. Expand the district below to see when and where work will take place and road closures.

Whilst we aim to be as accurate as possible with the below times and dates, there are instances where these may change at short notice.

Large-scale road maintenance

Our large-scale road maintenance involves reconstruction to replace the top layers of the road and provide a stable support for vehicle movement. Works include, where needed, vegetation clearance, drainage, signage and road markings.

Parish / Town Road Start date Duration
Cambridge Tennis Court Road 30 September 2024 Completed

Surface treatment work

We use different types of surface treatments to repair your roads, to learn why please visit our types of road surface treatment page.

Parish / Town Road Start date Duration Type of work
Coleridge Coleridge Road 21 October 2024 1 day. Road closures between 9.30am and 2.30pm Pre-surface treatment patching
Arbury Cockerell Road   Completed  
Arbury Barnard Way   Completed  
Arbury Hall Farm Road   Completed  
Cherry Hinton Queens Meadow   Completed  
Arbury Finch Road   Completed  
Arbury Topham Way   Completed  
Petersfield St Matthews Court   Completed  
Petersfield Petworth Street   Completed  
Cherry Hinton Geldart Street   Completed  
Cherry Hinton Wolsey Way   Completed  
Cherry Hinton Iver Close   Completed  
Coleridge Golding Road   Completed  
Trumpington Porson Road   Completed  
Trumpington Bentley Road   Completed  
Trumpington Diamond Close   Completed  
Trumpington Rayleigh Close   Completed  
Trumpington Newton Road   Completed  
Arbury Arbury   Completed  

Large-scale road maintenance

Our large-scale road maintenance involves reconstruction to replace the top layers of the road and provide a stable support for vehicle movement. Works include, where needed, vegetation clearance, drainage, signage and road markings.

Parish / Town Road Start date Duration
Ely Branch Bank 9 September 2024 Completed
Littleport Lynn Road 30 September 2024 Completed
Sutton B1381 Chain Causeway 6 January 2025 10 weeks. Working hours 8am to 6pm daily, may include weekends. Road closed day and night.
Upware, Swaffham Prior Prior Fen, Great Drove 1 March 2025  
Wicken Stretham Road To be confirmed  

Surface treatment work

We use different types of surface treatments to repair your roads, to learn why please visit our types of road surface treatment page.

Parish / Town Road Start date Duration Type of work
Haddenham Perry Close 28 September 2024 Completed Micro asphalt
Wilburton Bakery Close 28 September 2024 Completed Micro asphalt
Wilburton Toates Close 28 September 2024 Completed Micro asphalt
Wilburton Littlefield Close 28 September 2024 Completed Micro asphalt
Stretham Top Street 21 October 2024 Completed Micro asphalt
Ely Clay Way 21 October 2024 Completed Micro asphalt
Ely Ramsey Road 22 October 2024 Completed Micro asphalt
Ely Larkfield Road 23 October 2024 Completed Micro asphalt
Sutton Fairfield 24 October 2024 Completed Micro asphalt
Chippenham, Snailwell Snailwell Road, Palace Lane, Chippenham Road, The Green 11 November 2024 1 day. Road closures between 8am and 4pm. Pre-surface treatment patching
Ely High Barns, New Barns Avenue, New Barnes Road 12 November 2024 1 day. Road closures between 9.30am and 2.30pm. Pre-surface treatment patching
Coveney Main Street, Park Close, Gravel End 13 November 2024 2 days. Road closures between 9.30am and 2.30pm. Pre-surface treatment patching
Dullingham, Stetchworth, Westley Waterless, Little Wilbraham A1304 London Road 9 January 2025 2 nights. Road closures between 8pm and 6am. Pre-surface treatment patching
Stetchworth Hall Farm 13 January 2025 2 days. Road closures between 9.30am and 3.30pm. Pre-surface treatment patching
Ely, Little Thetford A10 Cambridge Road 15 January 2025 2 nights. Road closures between 8pm and 6am. Pre-surface treatment patching
Dullingham Station Road 17 January 2025 3 days. Road closures between 8am and 4pm. Pre-surface treatment patching
Wilburton Pools Road 31 January 2025 3 days. Road closures between 8am and 4pm. Pre-surface treatment patching
Burrough Green B1061 Bradley Road 5 February 2025 1 day. Road closures between 9.30am and 3.30pm. Pre-surface treatment patching
Wilburton A1123 Stretham Road   Completed  
Westley Waterless Brinkley Road   Completed  

Large-scale road maintenance

Our large-scale road maintenance involves reconstruction to replace the top layers of the road and provide a stable support for vehicle movement. Works include, where needed, vegetation clearance, drainage, signage and road markings.

Parish / Town Road Start date Duration
Christchurch Padgetts Road 16 September 2024 Completed
Manea Purls Bridge Drove 2 October 2024 Completed 
Benwick Ibbersons Drove 10 October 2024 Completed
Leverington Church Road, Church End, Roman Bank, Gorefield Road 4 November 2024 6 weeks. Proposed working hours 9.30am to 3pm, Monday to Friday.
Whittlesey Benwick Road 25 November 2024 10 weeks. Working hours 8am to 6pm daily, may include weekends. Road closed day and night.
Wisbech St Mary Garden Lane March 2025  
Chatteris Stocking Drove March 2025  
March Elm Road To be confirmed Working hours 8am to 5pm, Monday to Friday.
Whittlesey Eastrea Road To be confirmed Road closures between 8pm and 6am, Monday to Friday.

Surface treatment work

We use different types of surface treatments to repair your roads, to learn why please visit our types of road surface treatment page.

Parish / Town Road Start date Duration Type of work
Tydd St Giles B1165 Church Lane 6 December 2024 1 day. Road closures between 8am and 4pm Pre-surface treatment patching
Tipps End B1100 March Road 10 December 2024 3 days. Road closures between 8am and 4pm Pre-surface treatment patching
Wimblington King Street 20 February 2025 1 day. Road closures between 8am and 4pm Pre-surface treatment patching
Turves C71 Burnthouse Road 24 February 2025 3 days. Road closures between 8am and 4pm Pre-surface treatment patching
Leverington PE13 5JP Mill Lane   Completed  
Wisbech Windsor Drive   Completed  
Wisbech Prince of Wales Close   Completed  
Gorefield PE13 4NE Wolf Lane   Completed  
Tydd St Giles PE13 5ND Hannath Road   Completed  
Friday Bridge PE14 0LA Needham Bank   Completed  
Christchurch PE14 9HG Sixteen Foot Bank   Completed  
Chatteris PE16 6UZ Langwood Hill Drove   Completed  
Benwick PE15 0UX Doddington Road   Completed  
Whittlesey A605 Syres Lane   Completed  
Chatteris Fairview Crescent   Completed  
Chatteris Fairview Gardens   Completed  
Chatteris Fairview Avenue   Completed  
Chatteris Fairview Drive   Completed  

Large-scale road maintenance

Our large-scale road maintenance involves reconstruction to replace the top layers of the road and provide a stable support for vehicle movement. Works include, where needed, vegetation clearance, drainage, signage and road markings.

Parish / Town Road Start date Duration
Various Huntingdonshire A1307 27 August 2024 Completed
Fenstanton Conington Road 10 September 2024 Completed
Steeple Gidding Steeple Gidding Road 30 September 2024 Completed
Somersham Chatteris Road 16 October 2024 9 weeks. Working hours 8am to 6pm daily, may include weekends. Road closed day and night.
Huntingdon California Road 26 October 2024 Completed
Ramsey Great Whyte 4 November 2024 3 weeks. Road closures at night.
Holme New Long Drove 1 March 2025  
Farcet Kings Delph Road 1 March 2025 10 days. Working hours 8am to 6pm.

Surface treatment work

We use different types of surface treatments to repair your roads, to learn why please visit our types of road surface treatment page.

Parish / Town Road Start date Duration Type of work
Eaton Ford Keats Court 2 October 2024 Completed Micro asphalt
Eaton Ford Byron Place 2 October 2024 Completed Micro asphalt
Eaton Ford Browning Drive 2 October 2024 Completed Micro asphalt
Eaton Ford Masefield Avenue 3 October 2024 Completed Micro asphalt
Eaton Ford Chaucer Place 7 October 2024 Completed Micro asphalt
Eaton Ford Cowpers Court 8 October 2024 Completed Micro asphalt
Eaton Ford Tennyson Place 8 October 2024 Completed Micro asphalt
Eaton Ford Kipling Place 9 October 2024 Completed Micro asphalt
Eaton Ford Burns Court 10 October 2024 Completed Micro asphalt
Eaton Ford Longfellow Place 10 October 2024 Completed Micro asphalt
Eaton Ford Wordsworth Avenue 12 October 2024 Completed Micro asphalt
Eaton Ford Shelley Place 11 October 2024 Completed Micro asphalt
Eaton Ford Stevenson Court 11 October 2024 Completed Micro asphalt
Eaton Ford Spencer Close 12 October 2024 Completed Micro asphalt
Eaton Ford Marlowe Court 12 October 2024 Completed Micro asphalt
Eaton Ford Hardy Place 14 October 2024 Completed Micro asphalt
Eaton Ford Fielding Court 14 October 2024 Completed Micro asphalt
Eaton Ford Milton Avenue 16 October 2024 Completed Micro asphalt
Earith, Colne, Somersham B1050 Colne Road, Earith Road, Somersham Road 14 October 2024 2 days. Road closures between 9.30am and 2.30pm. Pre-surface treatment patching
Ramsey, Ramsey Forty Foot B1096 Wood Lane, B1096 Ramsey Road 16 October 2024 1 day. Road closures between 9.30am and 2.30pm. Pre-surface treatment patching
Yaxley Dovecote Lane 17 October 2024 2 days. Road closures between 8am and 4pm. Pre-surface treatment patching
Yaxley Church Street 21 October 2024 1 day. Road closures between 8am and 4pm. Pre-surface treatment patching
Yaxley Main Street, West End 22 October 2024 2 days. Road closures between 9.30am and 2.30pm. Pre-surface treatment patching
Wood Walton, Sawtry B1090 Walton Hill, B1090 Woodwalton Lane 18 November 2024 1 day. Road closures between 9.30am and 2.30pm. Pre-surface treatment patching
Fenstanton A1096 London Road 24 November 2024 1 day. Road closures between 8am and 5pm. Pre-surface treatment patching
Elton Bullock Road 25 November 2024 1 day. Road closures between 8am and 4pm. Pre-surface treatment patching
Hartford A141 Huntingdon Northern Bypass 4 December 2024 2 nights. Road closures between 8pm and 6am. Pre-surface treatment patching
Stilton Church Street 27 November 2024 3 days. Road closures between 9.30am and 2.30pm. Pre-surface treatment patching
Great Gidding, Glatton B660 Main Street, Winwick Road, Infield Road 20 January 2025 1 day. Road closures between 9.30am and 3.30pm. Pre-surface treatment patching
Folksworth, Stilton Washingley Lane, Lutton Road To be confirmed 1 day. Road closures between 8am and 4pm.  
Eaton Ford Coleridge Close    Completed Micro asphalt
Ramsey PE26 1DE Hollow Lane   Completed  
Upton PE28 5XP The Old North Road   Completed  
Ramsey Andrewes Close   Completed  
Catworth Princes Street   Completed  
Catworth Yeomans Close   Completed  
Farcet Marshalls Way   Completed  
Upton PE28 5XP The Old North Road   Completed  
Washingley PE7 3SJ Bullock Road   Completed  
Elton PE7 3SJ Warmington Road   Completed  
Ramsey PE26 1DE Hollow Lane   Completed  
Waresley PE19 6XE Drewels Lane   Completed  
Great Staughton PE28 0BX West Perry Road   Completed  
Ramsey C86 Muchwood Lane   Completed  
Alconbury C103 Monks Wood Road   Completed  
Warboys B1040 High St   Completed  
Kimbolton PE28 0JD Station Road   Completed  
Chesterton PE8 6SE Oundle Road   Completed  

Large-scale road maintenance

Our large-scale road maintenance involves reconstruction to replace the top layers of the road and provide a stable support for vehicle movement. Works include, where needed, vegetation clearance, drainage, signage and road markings.

Parish / Town Road Start date Duration
Madingley St Neots Road 17 September 2024 Completed
Gamlingay Church Street 28 October 2024 Completed
Milton Ely Road 28 October 2024 Completed
Croydon Croydon Hill 18 November 2024 2 weeks. 
Little Abington Cambridge Road 20 November 2024 3 weeks. Road closures between 8pm and 6am.
Bourn Alms Hill, High Street, Caxton End To be confirmed Working hours 8am to 5pm.
Caxton Gransden Road To be confirmed Working hours 7.30am to 6pm.
Bourn Broadway To be confirmed  

Surface treatment work

We use different types of surface treatments to repair your roads, to learn why please visit our types of road surface treatment page.

Parish / Town Road Start date Duration Type of work
Steeple Morden Cheyney Street 22 November 2024 4 days. Road closures between 9.30am and 2.30pm. Pre-surface treatment patching
Horseheath, Shudy Camps Horseheath Green, Cardinals Green, Mill Green 27 November 2024 3 days. Road closures between 8am and 4pm. Pre-surface treatment patching
Over, Longstanton Gravel Bridge Road, Over Road, Longstanton Road 18 December 2024 1 day. Road closures between 9.30am and 3.30pm. Pre-surface treatment patching
Fowlmere, Melbourn B1368 London Road 2 January 2025 1 day. Road closures between 9.30am and 2.30pm. Pre-surface treatment patching
Great Chishill May Street, Bogmoor Road 3 January 2025 4 days. Road closures between 8am and 4pm. Pre-surface treatment patching
Little Chishill Little Chishill Road 22 January 2025 7 days. Road closures between 8am and 4pm. Pre-surface treatment patching
Thriplow Gravel Pit Hill 3 February 2025 2 nights. Road closures between 8pm and 6am. Pre-surface treatment patching
West Wratting, Weston Colville B1052 Bull Lane 6 February 2025 2 days. Road closures between 9.30am and 2.30pm. Pre-surface treatment patching
Carlton, Brinkley Brinkley Road, Brinkley Road 12 February 2025 2 days. Road closures between 9.30am and 3.30pm. Pre-surface treatment patching
Histon Melvin Way 25 February 2025 1 day. Road closures between 8am and 4pm Pre-surface treatment patching
Waterbeach Spurgeons Avenue 26 February 2025 1 day. Road closures between 8am and 4pm Pre-surface treatment patching
Litlington Royston Road 3 March 2025 6 days. Road closures between 9.30am and 3.30pm. Pre-surface treatment patching
Fulbourn, Teversham Teversham Road, Fulbourn Road 10 March 2025 1 day. Road closures between 9.30am and 2.30pm. Pre-surface treatment patching
Great Shelford Granhams Road 17 March 2025 5 days. Road closures between 9.30am and 3.30pm. Pre-surface treatment patching
Oakington Dry Drayton Road To be confirmed Road closures between 9.30am and 2.30pm. Pre-surface treatment patching
Conington CB23 4LU New Barns Road   Completed  
Oakington CB23 8AL Dry Drayton Road   Completed  
Great Chishill B1039 Hall Lane   Completed  
Steeple Morden C73 Hay St   Completed  
Barton B1046 Comberton Road   Completed  
Steeple Morden SG8 0LY Litlington Road   Completed  
Steeple Morden SG8 0LY Litlington Road   Completed  
Bassingbourn SG8 5PG Fen Road   Completed  
Teversham Gazelle Way   Completed  
Oakington Dry Drayton Road   Completed  
Landbeach Waterbeach Road   Completed  
Horningsea Clayhithe Road   Completed  

Roadwork and traffic information

Our interactive map gives you more detail on the latest roadworks, road closures and diversions. Works listed on this page are included.

Visit our road and traffic information page to access the map and instructions on how to use. Details of upcoming roadworks in PDF format are also provided.

The map uses data from Causeway one.network. Enter your road name and see the types of work happening today or in the next two weeks, three or twelve months.

You can also follow us on X (formerly Twitter) for updates on where we are working - @Cambs_Traffic

Can't find what you are looking for?

If you are unable to find a scheme on this page, it may be part of our reactive or cyclical maintenance programmes.

These works are more area based and include gully cleansing, road patching and public rights of way maintenance.

FAQ

Please read through our frequently asked questions. If you are unable to find the answer please contact us.

The work area is the section of the road where our operatives will be working. The road closure area often extends beyond this to manage through traffic and divert it on to an alternative route. This helps us do the work quickly and efficiently, while keeping residents, road users and the workforce safe. 

If you receive information notifying you about a road closure, we will include a map which indicates both the work and road closure areas if these are different.

As the work involves heavy plant and equipment, we cannot guarantee you will be able to access your property without having to wait or access via the other end of the works.

If you normally drive into or out of the work area during the hours when the closure is in place, we may ask you to please make alternative arrangements.

We will often phase works to try to reduce the disruption this can cause, and the site team will be available to communicate with residents and businesses regarding this.

We will always maintain access to properties if it is safe to do so. Delays will sometimes be unavoidable when we must move machinery or equipment out of the way. We thank you for your patience and cooperation while this is done.

Work is phased to allow property access from at least one end of the road. Access may differ, depending on where we are working.

We place advance warning signs at the starting points of our works at least 14 days before the work starts.

We will inform residents and businesses which are located with the area of work, via letter or leaflet drop, at least 14 days in advance of work starting, wherever possible.

We try to keep noise to a minimum, and plan noisier working activities for earlier on in shifts where we are working at night in residential areas. However, the work is being delivered using heavy plant and machinery and this will cause noise and disruption whilst the work is on site, especially where we are working overnight. To try to limit this we:

  • Consider alternative ways of working, for example during the day, instead of night, when working in residential areas at the weekend.
  • Working reduced hours overnight. This approach often means a longer delivery programme, whereas working longer shifts will result in the work being completed quicker.
  • Working during the day whenever we can to reduce costs and disruption to residents during unsociable hours.

Provided your speed is under 20mph, you can use a treated road approximately 20 minutes after a treatment product has been applied.

Please take care when using a newly laid road surface as some loose chippings are likely.

Please follow any temporary speed limits in place.

We can only lay road surface treatments in good weather. If the ground is still wet, it is raining, too hot or too cold for the surface treatment to be effective, we must postpone works until the weather conditions improve. This is to ensure the work is long-lasting and successful.

The schedule on this page is updated regularly to reflect any changes.

When choosing a route to use for diverted traffic, we use the same category or a higher category road as the temporarily closed road. This is to ensure the diversion route can cope with the same type of traffic as the temporarily closed road.

In certain rural locations, if there is no suitable alternative, we may have to divert using a lower category route. Please note that we only signpost approved diversion routes.

Sometimes, road users may choose to use an alternative local road. We do not have the powers to prevent highway users from using these alternative routes.

Contact

To report an issue with a road, please visit our report a highways fault page.

If you have any queries or require any additional information please email: Local.Highways@cambridgeshire.gov.uk