Skip to main content

We maintain 1,000 of kilometres of drains and over 108,000 gullies across the county on behalf of our communities.

The information here provides details on the planned repairs to drainage systems across the county.

The scale and type of work will vary depending on the individual scheme and the repair being undertaken.

Drain cover at the side of a road

Most of our work will be delivered either under a full road closure or local traffic management system, such as traffic lights. This will cause disruption to the road network while we are on site. We will keep disruption to a minimum and we appreciate your cooperation during these critical works.

As well as the large-scale drain work, planned in advance, we also continually do reactive work across the whole county in response to issues that arise. This includes cyclical gully maintenance. By doing this, we keep the drain network flowing and identify any issues that need further investigation and repair.

We also regularly empty and clean gullies and pipes when they become blocked. We do this when we have identified a problem needing to be fixed through our routine inspections or when an issue is reported by a member of the public.

Planned work by district

Updates are provided monthly by officers. Expand the district to see details of when and where the work will take place, and details of road closures and diversion routes.

Whilst we aim to be as accurate as possible with the below times and dates, there are instances where these may change at short notice.

Our 2025/26 programme currently does not include any capital maintenance work here, but other reactive highways repairs are always being delivered. Find out more in FAQs.

Drainage projects

Planned works include repairs to existing drainage pipe and laying sections of new pipe. Plus installing new drainage systems, gullies, and manholes.

2025-2026 programmes

Parish / Town Road Start date Duration
       

2025-2026 design and investigation

Parish / Town Road
   

Cyclical drainage work

Our cyclical drainage work is undertaken every other year. Work involves jetting, emptying, and cleaning all gullies and drains.

2025-2026 programmes

Parish / Town Road Start Date Duration Actual completion date
       

Drainage projects

Planned works include repairs to existing drainage pipe and laying sections of new pipe, installing new drainage systems, gullies, and manholes.

2025-2026 programmes

Parish / Town Road Start date Duration
Littleport Sandhill To be confirmed 1 day
Littleport Sandhill 11 August 2025 Phase one completed

Cyclical drainage work

Our cyclical drainage work is undertaken every other year. Work involves jetting, emptying, and cleaning all gullies and drains.

2025-2026 programmes

Parish / Town Road Start Date Duration Actual completion date
Bottisham 7 July 2025 1.5 days 8 July 2025
Swaffham Bulbeck 9 July 2025 2 days 10 July 2025
Swaffham Prior 10 July 2025 1.5 days 11 July 2025
Lode 11 July 2025 1 day 11 July 2025
Reach 14 July 2025 0.4 days 14 July 2025
Burwell 14 July 2025 10.5 days 11 August 2025
Fordham 9 June 2025 5 days 13 June 2025
Chippenham 13 June 2025 0.5 days 13 June 2025
Kennet 13 June 2025 6 days 13 June 2025 
Snailwell 16  June 2025 0.5 days 16 June 2025
Brinkley 16 June 2025 1 day 16 June 2025
Westley Waterless 17 June 2025 0.5 days 17 June 2025
Burrough Green 17 June 2025 1.5 days 18 June 2025
Dullingham 18 June 2025 2 days 19 June 2025
Stetchworth 20 June 2025 2 days 23 June 2025
Woodditton 24 June 2025 3.5 days 27 June 2025
Cheveley 30 June 2025 3 days 2 July 2025
Ashley 3 July 2025 1 day 3 July 2025
Upend 4 July 2025 0.5 days 4 July 2025
Kirtling and Saxon Street 4 July 2025 0.5 days 4 July 2025
Coveney 13 October 2025 0.5 days 13 October 2025
Witcham 13 October 2025 1 day 13 October 2025
Mepal 13 October 2025 2 days 15 October 2025
Haddenham 15 October 2025 4 days 20 October 2025
Aldreth 15 October 2025 4 days 20 October 2025
Wilburton 21 October 2025 1.5 days 22 October 2025
Stretham 22 October 2025 2.5 days 24 October 2025
Little Thetford 22 October 2025 2.5 days 24 October 2025
Sutton 24 October 2025 6 days 31 October 2025
Wardy Hill 3 November 2025 2 days 4 November 2025
Ely North including Prickwillow, Queen Adelaide and Chettisham 12 March 2026    
Ely East including Stuntney 16 March 2026    

Drainage grips

We make cuts into roadside verges so surface water can run off the road into a ditch. The cuts are called drainage grips.

2025-2026 programme

Parish / Town Road Extent of work Start date Actual completion date
Isleham Prickwillow Road From Isleham Coates Drove to Prickwillow B1382 Ely Road To be confirmed To be confirmed
Snailwell Chippenham Road From Chippenham High Street to Snailwell Newmarket Road To be confirmed To be confirmed
Soham Broad Piece From Mereside to The Coates To be confirmed To be confirmed
Soham Hasse Road From A142 to Northfield Road To be confirmed To be confirmed
Stetchworth Stetchworth Road From Woodditton From 30mph to Stetchworth 30mph To be confirmed To be confirmed
Dullingham Station Road From A1304 to Eagle Lane To be confirmed To be confirmed
A1304 Six Mile Bottom From 40mph Six Mile Bottom to race course roundabout To be confirmed To be confirmed
Newmarket Duchess Drive From Jarman Centre to Saxon Street To be confirmed To be confirmed
Borrough green B1061 From Borrough Green 40mph to county boundary To be confirmed To be confirmed
Stretham Green End From Cross Drove to Newmarket Road To be confirmed To be confirmed
Sutton B1381 From Sutton to A1123 junction To be confirmed To be confirmed
Pymoor Pymoor Lane From Main Street to Black Bank Road To be confirmed To be confirmed
Coveney Wayhead From Gravel End Road to High Road (old Lynn Road) To be confirmed To be confirmed
Coveney Jerusalem Drove From The Green to Mepal Road To be confirmed To be confirmed
Ely Queen Adelaide Way Prickwillow Road to Station Road To be confirmed To be confirmed
Prickwillow Mile End Road Mildenhall Road to Prickwillow To be confirmed To be confirmed
Soham Padney Drove   To be confirmed To be confirmed
Dullingham Cross Green Full length To be confirmed To be confirmed
Ely Queen Adelaide Way Prickwillow Road to Station Road To be confirmed To be confirmed
Ely Angel Drove Between roundabouts To be confirmed To be confirmed
Ely Downham Road (A10) A10 to Little Downham To be confirmed To be confirmed
Prickwillow Ely Road Queen Adelaide to Putney Hill Road junction To be confirmed To be confirmed
Prickwillow Mile End Road Mildenhall Road to Prickwillow To be confirmed To be confirmed
Little Downham Westmoor Common Cophall Drove to Main Street To be confirmed To be confirmed
Little Downham Second Drove Full length To be confirmed To be confirmed
Little Downham Third Drove Full length To be confirmed To be confirmed
Little Downham Mill Hill From Cophall Drove to High Street junction To be confirmed To be confirmed
Little Downham California Lawn Lane to Black Bank Road To be confirmed To be confirmed
Little Downham Fourth Drove Full length To be confirmed To be confirmed
Little Downham Cowbridge Hall Drove Ely Road to Bield Drove To be confirmed To be confirmed
Little Downham Pymoor Lane Full length To be confirmed To be confirmed
Littleport A1101 Wisbech Road A10 to Burnt Chimney Drove To be confirmed To be confirmed
Littleport Mildenhall Road New River Bank to Shippea Hill To be confirmed To be confirmed
Littleport Branch Bank A1101 Mildenhall Road to Ely Road To be confirmed To be confirmed
Littleport Ely Road The Coppice Littleport to The Hamlet Chettisham To be confirmed To be confirmed
Ely A10 Witchford round about to Norfolk border To be confirmed To be confirmed
Milton A10 A14 Milton to A142 Witchford roundabout To be confirmed To be confirmed

Drainage projects

Planned works include repairs to existing drainage pipe and laying sections of new pipe, installing new drainage systems, gullies, and manholes.

2025-2026 programmes

Parish / Town Road Start date Duration
Gorefield Gote Lane 11 August 2025 Completed
Parson Drove Fen Road 6 October 2025 10 weeks. Working hours between 8am and 5pm, Monday to Friday.
Leverington Roman Bank 29 November 2025 2 days. Working hours between 8am and 6pm.
Chatteris Eden Crescent To be confirmed  

2025-2026 design and investigation

Parish / Town Road
 March Butt Avenue and Brewin Avenue

Cyclical drainage work

Our cyclical drainage work is undertaken every other year. Work involves jetting, emptying, and cleaning all gullies and drains.

2025-2026 programmes

Parish / Town Road Start Date Duration Actual completion date
Wimblington 19 May 2025 6.5 days 27 May 2025
Doddington 27 May 2025 6 days 3 June 2025
Benwick 4 June 2025 3.5 days 6 June 2025
Chatteris To be confirmed    
Parsons Drove 22 April 2025 1.5 days 23 April 2025
Wisbech St Mary 23 April 2025 4 days 28 April 2025
Guyhirn 29 April 2025 2 days 30 April 2025
Murrow 1 May 2025 2 days 02 May 2025
Elm 5 May 2025 5.5 days 12 May 2025
Coldham 12 May 2025 0.5 days 12 May 2025
Rings End 13 May 2025 1 day 13 May 2025
Friday Bridge 14 May 2025 3 days 16 May 2025
Wimblington 19 May 2025 7 days 27 May 2025
Doddington 27 May 2025 6 days 3 June 2025
Benwick 4 June 2025 2 days 6 June 2025
March 20 October 2025 44.5 days  
Manea 9 December 2025    
Christchurch 12 December 2025    
Whittlesey 21 January 2026    
Ponders Bridge 10 March 2026    
Turves 11 March 2026    
Eastrea 11 March 2026    
Coates 12 March 2026    
Burnt House Bridge 13 March 2026    
16 Foot Drain 16 March 2026    
Beggars Bridge 16 March 2026    

Drainage grips

We make cuts into roadside verges so surface water can run off the road into a ditch. The cuts are called drainage grips.

2025-2026 programme

Parish / Town Road Extent of work Start date Actual completion date
Chatteris Langwood Hall Drove From A142 to Byall Fen Road 23 June 2025 23 June 2025
Chatteris New Road From A142 to Byall Fen Road 23 June 2025 24 June 2025
Guyhirn A141 From Huntingdon to Guyhirn 27 October 2025 7 November 2025
Manea Byall Fen Drove From Langwood Hill Drove to Fallow Corner Drove 24 June 2025 25 June 2025
March B1101 From Longhill Road to Friday Bridge 8 July 2025 11 July 2025
Chatteris Langwood Fen Drove From Langwood Hill Drove to Block Fen Drove 26 June 2025 26 June 2025
Wimblington Knights End Road From A141 to B1093 25 July 2025 31 July 2025
Doddington Dykemoor Drove From Primrose Hill to B1093 10 July 2025 31 July 2025
Chatteris Doddington Road From A141 to Primrose Hill 16 July 2025 18 July 2025
Chatteris A142 From A141 Chatteris to A10 13 October 2025 17 October 2025
Friday bridge March Coldham Bank Full length To be confirmed To be confirmed
Christchurch Padgetts Road Full length To be confirmed To be confirmed
Benwick Ibbersons Drove From Forty Foot to B1096 To be confirmed To be confirmed
Wisbech Barton Road From Bovis Lane To be confirmed To be confirmed
Christchurch Upwell Road Full length To be confirmed To be confirmed
Manea Fifty Road Full length To be confirmed To be confirmed
Chatteris Sixteen Foot Bank Full length To be confirmed To be confirmed
Benwick Whittlesey Road Full length To be confirmed To be confirmed
Turves Cock Bank Full length To be confirmed To be confirmed
Whittlesey Benwick Road Full length To be confirmed To be confirmed
Whittlesey Ramsey Road Full length To be confirmed To be confirmed
Whittlesey East Delph   To be confirmed To be confirmed
March Isle of Ely Way   To be confirmed To be confirmed
Wimblington Manea Road From B1098 Sixteen Foot Bank to A141 Isle of Ely Way To be confirmed To be confirmed

Drainage projects

Planned works include repairs to existing drainage pipe and laying sections of new pipe, installing new drainage systems, gullies, and manholes.

2025-2026 programmes

Parish / Town Road Start date Duration
Great Paxton High Street 7 July 2025 Completed
Great Gransden East Street and Middle Street 7 July 2025 9 weeks. Working hours between 7am and 7pm, Monday to Friday
Stilton North Street and High Street 5 January 2026 18 weeks. Working hours between 7am and 7pm, Monday to Friday
Fenstanton Manor Drive, Hall Green Lane 6 January 2026  
Huntingdon St Johns Street 18 January 2026 3 nights. Working hours between 8pm and 6am.
Needingworth Hawkes Lane 2 April 2026  
Fenstanton Greenfields 17 April 2026  
Chesterton Oundle Road To be confirmed  
Yaxley Broadway To be confirmed  
Somersham Parkhall Road To be confirmed  

2025-2026 design and investigation

Parish / Town Road
Brampton Buckden Road
Hemingford Abbots Various

Cyclical drainage work

Our cyclical drainage work is undertaken every other year. Work involves jetting, emptying, and cleaning all gullies and drains.

2025-2026 programmes

Parish / Town Road Start Date Duration Actual completion date
Holme 28 July 2025 1.5 days 12 August 2025
Glatton 30 July 2025 1 day 13 August 2025
Connington 30 July 2025 1 day 14 August 2025
Sawtry 14 August 2025 20.5 days 3 October 2025
Woodwalton 6 October 2025 1 day 6 October 2025
Great Gidding 6 October 2025 1 day 7 October 2025
Little Gidding 7 October 2025 0.5 days 7 October 2025
Hamerton and Steeple Gidding 8 October 2025 0.5 days 9 October 2025
Winwick 8 October 2025 0.5 days 8 October 2025
Old Weston 9 October 2025 1 day 9 October 2025
Brington and Molesworth 10 October 2025 1 day 10 October 2025
Bythorn and Keyston 13 October 2025 0.5 days 14 October 2025
Catworth 14 October 2025 1 day 15 October 2025
Spaldwick 15 October 2025 1.5 days 15 October 2025
Ellington 16 October 2025 1.5 days 17 October 2025
Stow Longa 17 October 2025 0.5 days 17 October 2025
Covington 4 November 2025 0.5 days 4 November 2025
Tilbrook 4 November 2025 0.5 days 4 November 2025
Kimbolton 5 November 2025 2.5 days 7 November 2025
Grafham 7 November 2025 1 day 10 November 2025
Perry East and West 10 November 2025 2 days 11 November 2025
Buckden 11 November 2025 4 days  17 November 2025
Offord Cluny 17 November 2025 2.5 days 19 November 2025
Offord D'Arcy 19 November 2025 0.5 days 19 November 2025
Southoe 20 November 2025 1 day 20 November 2025
Great Paxton 21 November 2025 2 days 24 November 2025
Little Paxton 24 November 2025 4.5 days 28 November 2025
Hail Weston 28 November 2025 1.5 days  
Great Staughton 1 December 2025 1.5 days  
Diddington 2 December 2025 0.5 days  
St Neots 3 December 2025 46 days  
Abbots Ripton 2 January 2026 0.5 days  
Alconbury Weston 5 January 2026 1.5 days  
Alconbury 6 January 2026 3.5 days  
Broughton 12 January 2026 0.5 days  
Kings Ripton 12 January 2026 0.5 days  
Upton 12 January 2026 0.5 days  
Coppingford Road 12 January 2026 0.5 days  
The Stukeleys 13 January 2026 2 days  
Brampton 15 January 2026 10 days  
Huntingdon 29 January 2026 32 days  

Drainage grips

We make cuts into roadside verges so surface water can run off the road into a ditch. The cuts are called drainage grips.

2025-2026 programme

Parish / Town Road Extent of work Start date Actual completion date
Ramsey St Mary B1040 From Ponders Bridge to Huntingdon Road 1 August 2025 5 August 2025
Godmanchester Silver Street From number 40 to playground To be confirmed To be confirmed
Abbotsley Pitsdean Road From Blacksmiths Lane to speed limit To be confirmed To be confirmed

Drainage projects

Planned works include repairs to existing drainage pipe and laying sections of new pipe. Plus installing new drainage systems, gullies, and manholes.

2025-2026 programmes

Parish / Town Road Start date Duration
Linton High Street To be confirmed 3 weeks
Linton Lamb Fair Court To be confirmed  

2025-2026 design and investigation

Parish / Town Road
Fulbourn Station Road
Great Wilbraham Church Street
Little Wilbraham High Street
Waterbeach Chapel Street

Cyclical drainage work

Our cyclical drainage work is undertaken every other year. Work involves jetting, emptying, and cleaning all gullies and drains.

2025-2026 programme

Parish / Town Road Start Date Duration Actual completion date
Teversham 28 April 2025 4 days 1 May 2025
Little Wilbraham 1 May 2025 0.5 days 1 May 2025
Great Wilbraham 2 May 2025 1.5 days 5 May 2025
Fulbourn 5 May 2025 6 days 12 May 2025
Weston Colville 13 May 2025 1 day 13 May 2025
Carlton 13 May 2025 1 day 14 May 2025
West Wratting 14 May 2025 0.5 days 14 May 2025
Balsham 15 May 2025 3 days 19 May 2025
West Wickham and Streetly End 20 May 2025 1 day 20 May 2025
Hildersham 20 May 2025 0.5 days 20 May 2025
Linton 21 May 2025 5 days 27 May 2025
Horseheath and Cardinals Green 28 May 2025 1 days 28 May 2025
Bartlow 28 May 2025 0.5 days 28 May 2025
Shudy Camps 29 May 2025 0.5 days 29 May 2025
Castle Camps 29 May 2025 0.5 days 29 May 2025
Willingham 30 May 2025 6 days 6 June 2025
Rampton 6 June 2025 1 day 6 June 2025
Cottenham 9 June 2025 6.5 days 17 June 2025
Longstanton 17 June 2025 8.5 days 1 August 2025
Oakington and Westwick 30 June 2025 3.5 days 7 August 2025
Histon 3 July 2025 6 days 14 August 2025
Impington 11 July 2025 7.5 days 25 August 2025
Girton 22 July 2025 4.5 days 29 August 2025
Croxton 28 July 2025 2 days 25 August 2025
Eltisley 28 July 2025 1.1 days 25 August 2025
Caxton 29 July 2025 2.5 days 28 August 2025
Cambourne 31 July 2025 12.5 days 15 September 2025
Little Gransden 19 August 2025 0.5 days 16 September 2025
Longstowe 19 August 2025 1 day 17 September 2025
Gamlingay 18 September 2025 6 days 25 September 2025
Hatley St George and East Hatley 26 September 2025 0.5 days 26 September 2025
Croyden 26 September 2025 0.5 days 26 September 2025
Arrington 26 September 2025 1 day 29 September 2025
Tadlow 29 September 2025 2 days 29 September 2025
Shingay Cum Wendy 30 September 2025 0.5 days 30 September 2025
Guilden Morden 30 September 2025 1.5 days 1 October 2025
Steeple Morden 2 October 2025 1.5 days 3 October 2025
Abington Piggots 3 October 2025 0.5 days 3 October 2025
Litlington 3 October 2025 1 day 6 October 2025
Bassingbourn 6 October 2025 4.5 days 10 October 2025
Connington 27 November 2025 0.5 days  
Knapwell 17 February 2026 0.5 days  
Bar Hill 17 February 2026 7 days  
Fen Drayton 19 February 2026 1 day  
Dry Drayton 26 February 2026 1.5 days  
Madingley 2 March 2026 0.5 days  
Papworth Everard 2 March 2026 9 days  
Over 13 March 2026 4.5 days  
Swavesey 20 March 2026 5 days  
Boxworth 27 March 2026 0.5 days  
Lolworth 27 March 2026 0.5 days  
Graveley 27 March 2026 0.5 days  
Papworth St Agnes 30 March 2026 0.5 days  
Elsworth 30 March 2026 1 day  

Drainage grips

We make cuts into roadside verges so surface water can run off the road into a ditch. The cuts are called drainage grips.

2025-2026 programme

Parish / Town Road Extent of work Start date Actual completion date
B1052 Linton Balsham Road From Linton 30mph to Balsham 30mph 10 September 2025 12 September 2025
Balsham West Wickham Road From Balsham 30mph to Horseheath 30mph 15 September 2025 15 September 2025
West Wickham Skippers Lane From boundary to the common 15 September 2025 15 September 2025
West Wratting Six Mile Bottom From Honey Hill to London Road 15 September 2025 16 September 2025
Shudy Camps Mill Green From Horseheath Green to Nosterfield End 16 September 2025 16 September 2025
Castle Camps Bartlow Road From Castle Camps 30mph to Bartlow 30mph 16 September 2025 17 September 2025
Bartlow Dean Road From Bartlow 30mph to West Wickham road cross roads 17 September 2025 18 September 2025
A1307 A1307 From Suffolk boundary to Cambridge Hinton Way roundabout 6 November 2025 14 November 2025
Foxton Fowlmere Road From Cambridge road to Foxton village 26 September 2025 26 September 2025
Barrington Foxton Road From Barrington 30mph to A10 26 September 2025 29 September 2025
B1368 Barley From county boundary to A10 To be confirmed To be confirmed
Foxton Shepreth Road From 30mph to A10 junction 6 October 2025 7 October 2025
Haslingfield Barton Road From Haslingfield 30mph to A603 Barton To be confirmed To be confirmed
Swavesey Fen Drayton Road From Gibraltar lane to Rose and Crown Road To be confirmed To be confirmed
Swavesey Ramper Road From Boxworth end to B1050 To be confirmed To be confirmed
Fulbourn Shelford Road From 30mph to junction with Cherry Hinton Road To be confirmed To be confirmed
Newton High Road Full length To be confirmed To be confirmed
Cottenham Oakington road From orchard close to Guided bus To be confirmed To be confirmed

Roadwork and traffic information

Our interactive map gives you more detail on the latest roadworks, road closures and diversions. Works listed on this page are included.

Visit our road and traffic information page to access the map and instructions on how to use. Details of upcoming roadworks in PDF format are also provided.

The map uses data from Causeway one.network. Enter your road name and see the types of work happening today or in the next two weeks, three or twelve months.

You can also follow us on X (formerly Twitter) for updates on where we are working - @Cambs_Traffic

Can't find what you are looking for?

If you are unable to find a scheme on this page, it may be part of our reactive or cyclical maintenance programmes.

These works are more area based and include gully cleansing, road patching and public rights of way maintenance.

You can find out more about the county-wide road resurfacing programme on our Road improvements page.

FAQ

Please read through our frequently asked questions. If you are unable to find the answer please contact us.

The work area is the section of the road where our operatives will be working. The road closure area often extends beyond this to manage through traffic and divert it on to an alternative route. This helps us do the work quickly and efficiently, while keeping residents, road users and the workforce safe. 

If you receive information notifying you about a road closure, we will include a map which indicates both the work and road closure areas if these are different.

As the work involves heavy plant and equipment, we cannot guarantee you will be able to access your property without having to wait or access via the other end of the works.

If you normally drive into or out of the work area during the hours when the closure is in place, we may ask you to please make alternative arrangements.

We will often phase works to try to reduce the disruption this can cause, and the site team will be available to communicate with residents and businesses regarding this.

We will always maintain access to properties if it is safe to do so. Delays will sometimes be unavoidable when we must move machinery or equipment out of the way. We thank you for your patience and cooperation while this is done.

Work is phased to allow property access from at least one end of the road. Access may differ, depending on where we are working.

We place advance warning signs at the starting points of our works at least 14 days before the work starts.

We will inform residents and businesses which are located with the area of work, via letter or leaflet drop, at least 14 days in advance of work starting, wherever possible.

We try to keep noise to a minimum, and plan noisier working activities for earlier on in shifts where we are working at night in residential areas. However, the work is being delivered using heavy plant and machinery and this will cause noise and disruption whilst the work is on site, especially where we are working overnight. To try to limit this we:

  • Consider alternative ways of working, for example during the day, instead of night, when working in residential areas at the weekend.
  • Working reduced hours overnight. This approach often means a longer delivery programme, whereas working longer shifts will result in the work being completed quicker.
  • Working during the day whenever we can to reduce costs and disruption to residents during unsociable hours.

Contact

To report an issue with a drain or gully, please visit our report a highways fault page.

If you have any queries or require any additional information please email: highways@cambridgeshire.gov.uk

Capital maintenance programme

For more information on the workstreams covered please visit our capital maintenance programme page

How we are improving highways maintenance

Over the past two years, we have made the biggest investment in the highways network in over a decade, and it is important to show you where your money is spent.

Visit how we are improving highways maintenance. This page outlines our priorities, what improvements were made in 2024/25, and funding allocation for 2025/26.