We maintain 1,000 of kilometres of drains and over 108,000 gullies across the county on behalf of our communities.
The information here provides details on the planned repairs to drainage systems across the county.
The scale and type of work will vary depending on the individual scheme and the repair being undertaken.

Most of our work will be delivered either under a full road closure or local traffic management system, such as traffic lights. This will cause disruption to the road network while we are on site. We will keep disruption to a minimum and we appreciate your cooperation during these critical works.
As well as the large-scale drain work, planned in advance, we also continually do reactive work across the whole county in response to issues that arise. This includes cyclical gully maintenance. By doing this, we keep the drain network flowing and identify any issues that need further investigation and repair.
We also regularly empty and clean gullies and pipes when they become blocked. We do this when we have identified a problem needing to be fixed through our routine inspections or when an issue is reported by a member of the public.
Planned work by district
Updates are provided monthly by officers. Expand the district to see details of when and where the work will take place, and details of road closures and diversion routes.
Whilst we aim to be as accurate as possible with the below times and dates, there are instances where these may change at short notice.
Our 2025/26 programme currently does not include any capital maintenance work here, but other reactive highways repairs are always being delivered. Find out more in FAQs.
Drainage projects
Planned works include repairs to existing drainage pipe and laying sections of new pipe. Plus installing new drainage systems, gullies, and manholes.
2025-2026 programmes
Parish / Town | Road | Start date | Duration |
---|---|---|---|
2025-2026 design and investigation
Parish / Town | Road |
---|---|
Coleridge / Romsey | Burnside |
Cyclical drainage work
Our cyclical drainage work is undertaken every other year. Work involves jetting, emptying, and cleaning all gullies and drains.
2025-2026 programmes
Parish / Town Road | Start Date | Duration | Actual completion date |
---|---|---|---|
Drainage projects
Planned works include repairs to existing drainage pipe and laying sections of new pipe, installing new drainage systems, gullies, and manholes.
2025-2026 programmes
Parish / Town | Road | Start date | Duration |
---|---|---|---|
Littleport | Sandhill | 11 August 2025 | 1 week. Working hours 8am to 6pm. |
Cyclical drainage work
Our cyclical drainage work is undertaken every other year. Work involves jetting, emptying, and cleaning all gullies and drains.
2025-2026 programmes
Parish / Town Road | Start Date | Duration | Actual completion date |
---|---|---|---|
Bottisham | 7 July 2025 | 1.5 days | 8 July 2025 |
Swaffham Bulbeck | 9 July 2025 | 2 days | 10 July 2025 |
Swaffham Prior | 10 July 2025 | 1.5 days | 11 July 2025 |
Lode | 11 July 2025 | 1 day | 11 July 2025 |
Reach | 14 July 2025 | 0.4 days | 14 July 2025 |
Burwell | 14 July 2025 | 10.5 days | 11 August 2025 |
Fordham | 9 June 2025 | 5 days | 13 June 2025 |
Chippenham | 13 June 2025 | 0.5 days | 13 June 2025 |
Kennet | 13 June 2025 | 6 days | 13 June 2025 |
Snailwell | 16 June 2025 | 0.5 days | 16 June 2025 |
Brinkley | 16 June 2025 | 1 day | 16 June 2025 |
Westley Waterless | 17 June 2025 | 0.5 days | 17 June 2025 |
Burrough Green | 17 June 2025 | 1.5 days | 18 June 2025 |
Dullingham | 18 June 2025 | 2 days | 19 June 2025 |
Stetchworth | 20 June 2025 | 2 days | 23 June 2025 |
Woodditton | 24 June 2025 | 3.5 days | 27 June 2025 |
Cheveley | 30 June 2025 | 3 days | 2 July 2025 |
Ashley | 3 July 2025 | 1 days | 3 July 2025 |
Upend | 4 July 2025 | 0.5 days | 4 July 2025 |
Kirtling and Saxon Street | 4 July 2025 | 0.5 days | 4 July 2025 |
Coveney | To be confirmed | ||
Witcham | To be confirmed | ||
Mepal | To be confirmed | ||
Haddenham | To be confirmed | ||
Wilburton | To be confirmed | ||
Stretham | To be confirmed | ||
Sutton | To be confirmed | ||
Wardy Hill | To be confirmed | ||
Aldreth | To be confirmed | ||
Ely North including Prickwillow, Queen Adelaide and Chettisham | To be confirmed | ||
Ely East including Stuntney | To be confirmed |
Drainage grips
We make cuts into roadside verges so surface water can run off the road into a ditch. The cuts are called drainage grips.
2025-2026 programme
Parish / Town | Road | Extent of work | Start date | Actual completion date |
---|---|---|---|---|
Isleham | Prickwillow Road | From Isleham Coates Drove to Prickwillow B1382 Ely Road | To be confirmed | To be confirmed |
Snailwell | Chippenham Road | From Chippenham High Street to Snailwell Newmarket Road | To be confirmed | To be confirmed |
Soham | Broad Piece | From Mereside to The Coates | To be confirmed | To be confirmed |
Soham | Hasse Road | From A142 to Northfield Road | To be confirmed | To be confirmed |
Stetchworth | Stetchworth Road | From Woodditton From 30mph to Stetchworth 30mph | To be confirmed | To be confirmed |
Dullingham | Station Road | From A1304 to Eagle Lane | To be confirmed | To be confirmed |
A1304 | Six Mile Bottom | From 40mph Six Mile Bottom to race course roundabout | To be confirmed | To be confirmed |
Newmarket | Duchess Drive | From Jarman Centre to Saxon Street | To be confirmed | To be confirmed |
Borrough green | B1061 | From Borrough Green 40mph to county boundary | To be confirmed | To be confirmed |
Stretham | Green End | From Cross Drove to Newmarket Road | To be confirmed | To be confirmed |
Sutton | B1381 | From Sutton to A1123 junction | To be confirmed | To be confirmed |
Pymoor | Pymoor Lane | From Main Street to Black Bank Road | To be confirmed | To be confirmed |
Coveney | Wayhead | From Gravel End Road to High Road (old Lynn Road) | To be confirmed | To be confirmed |
Coveney | Jerusalem Drove | From The Green to Mepal Road | To be confirmed | To be confirmed |
Ely | Queen Adelaide Way | Prickwillow Road to Station Road | To be confirmed | To be confirmed |
Prickwillow | Mile End Road | Mildenhall Road to Prickwillow | To be confirmed | To be confirmed |
Soham | Padney Drove | To be confirmed | To be confirmed | |
Dullingham | Cross Green | Full length | To be confirmed | To be confirmed |
Ely | Queen Adelaide Way | Prickwillow Road to Station Road | To be confirmed | To be confirmed |
Ely | Angel Drove | Between roundabouts | To be confirmed | To be confirmed |
Ely | Downham Road (A10) | A10 to Little Downham | To be confirmed | To be confirmed |
Prickwillow | Ely Road | Queen Adelaide to Putney Hill Road junction | To be confirmed | To be confirmed |
Prickwillow | Mile End Road | Mildenhall Road to Prickwillow | To be confirmed | To be confirmed |
Little Downham | Westmoor Common | Cophall Drove to Main Street | To be confirmed | To be confirmed |
Little Downham | Second Drove | Full length | To be confirmed | To be confirmed |
Little Downham | Third Drove | Full length | To be confirmed | To be confirmed |
Little Downham | Mill Hill | From Cophall Drove to High Street junction | To be confirmed | To be confirmed |
Little Downham | California | Lawn Lane to Black Bank Road | To be confirmed | To be confirmed |
Little Downham | Fourth Drove | Full length | To be confirmed | To be confirmed |
Little Downham | Cowbridge Hall Drove | Ely Road to Bield Drove | To be confirmed | To be confirmed |
Little Downham | Pymoor Lane | Full length | To be confirmed | To be confirmed |
Littleport | A1101 Wisbech Road | A10 to Burnt Chimney Drove | To be confirmed | To be confirmed |
Littleport | Mildenhall Road | New River Bank to Shippea Hill | To be confirmed | To be confirmed |
Littleport | Branch Bank | A1101 Mildenhall Road to Ely Road | To be confirmed | To be confirmed |
Littleport | Ely Road | The Coppice Littleport to The Hamlet Chettisham | To be confirmed | To be confirmed |
Ely | A10 | Witchford round about to Norfolk border | To be confirmed | To be confirmed |
Milton | A10 | A14 Milton to A142 Witchford roundabout | To be confirmed | To be confirmed |
Drainage projects
Planned works include repairs to existing drainage pipe and laying sections of new pipe, installing new drainage systems, gullies, and manholes.
2025-2026 programmes
Parish / Town | Road | Start date | Duration |
---|---|---|---|
Gorefield | Gote Lane | 11 August 2025 | 7 weeks |
Leverington | Roman Bank | 2 September 2025 | 12 weeks |
Parson Drove | Fen Road | 22 September 2025 | 7 weeks |
Chatteris | Eden Crescent | To be confirmed |
2025-2026 design and investigation
Parish / Town | Road |
---|---|
March | Butt Avenue and Brewin Avenue |
Cyclical drainage work
Our cyclical drainage work is undertaken every other year. Work involves jetting, emptying, and cleaning all gullies and drains.
2025-2026 programmes
Parish / Town Road | Start Date | Duration | Actual completion date |
---|---|---|---|
Wimblington | 19 May 2025 | 6.5 days | 27 May 2025 |
Doddington | 27 May 2025 | 6 days | 3 June 2025 |
Benwick | 4 June 2025 | 3.5 days | 6 June 2025 |
Chatteris | To be confirmed | ||
Parsons Drove | 22 April 2025 | 1.5 days | 23 April 2025 |
Wisbech St Mary | 23 April 2025 | 4 days | 28 April 2025 |
Guyhirn | 29 April 2025 | 2 days | 30 April 2025 |
Murrow | 1 May 2025 | 2 days | 02 May 2025 |
Elm | 5 May 2025 | 5.5 days | 12 May 2025 |
Coldham | 12 May 2025 | 0.5 days | 12 May 2025 |
Rings End | 13 May 2025 | 1 day | 13 May 2025 |
Friday Bridge | 14 May 2025 | 3 days | 16 May 2025 |
March | To be confirmed | ||
Manea | To be confirmed | ||
Christchurch | To be confirmed | ||
Wimblington | To be confirmed | ||
Doddington | To be confirmed | ||
Benwick | To be confirmed | ||
Whittlesey | To be confirmed | ||
Ponders Bridge | To be confirmed | ||
Turves | To be confirmed | ||
Eastrea | To be confirmed | ||
Coates | To be confirmed | ||
Burnt House Bridge | To be confirmed | ||
16 Foot Drain | To be confirmed | ||
Beggars Bridge | To be confirmed |
Drainage grips
We make cuts into roadside verges so surface water can run off the road into a ditch. The cuts are called drainage grips.
2025-2026 programme
Parish / Town | Road | Extent of work | Start date | Actual completion date |
---|---|---|---|---|
Chatteris | Langwood Hall Drove | From A142 to Byall Fen Road | To be confirmed | To be confirmed |
Chatteris | New Road | From A142 to Byall Fen Road | To be confirmed | To be confirmed |
Guyhirn | A141 | From Huntingdon to Guyhirn | To be confirmed | To be confirmed |
Manea | Byall Fen Drove | From Langwood Hill Drove to Fallow Corner Drove | To be confirmed | To be confirmed |
March | B1101 | From Longhill Road to Friday Bridge | To be confirmed | To be confirmed |
Chatteris | Langwood Fen Drove | From Langwood Hill Drove to Block Fen Drove | To be confirmed | To be confirmed |
Wimblington | Knights End Road | From A141 to B1093 | To be confirmed | To be confirmed |
Doddington | Dykemoor Drove | From Primrose Hill to B1093 | To be confirmed | To be confirmed |
Chatteris | Doddington Road | From A141 to Primrose Hill | To be confirmed | To be confirmed |
Chatteris | A142 | From A141 Chatteris to A10 | To be confirmed | To be confirmed |
Friday bridge March | Coldham Bank | Full length | To be confirmed | To be confirmed |
Christchurch | Padgetts Road | Full length | To be confirmed | To be confirmed |
Benwick | Ibbersons Drove | From Forty Foot to B1096 | To be confirmed | To be confirmed |
Wisbech | Barton Road | From Bovis Lane | To be confirmed | To be confirmed |
Christchurch | Upwell Road | Full length | To be confirmed | To be confirmed |
Manea | Fifty Road | Full length | To be confirmed | To be confirmed |
Chatteris | Sixteen Foot Bank | Full length | To be confirmed | To be confirmed |
Benwick | Whittlesey Road | Full length | To be confirmed | To be confirmed |
Turves | Cock Bank | Full length | To be confirmed | To be confirmed |
Whittlesey | Benwick Road | Full length | To be confirmed | To be confirmed |
Whittlesey | Ramsey Road | Full length | To be confirmed | To be confirmed |
Whittlesey | East Delph | To be confirmed | To be confirmed | |
March | Isle of Ely Way | To be confirmed | To be confirmed | |
Wimblington | Manea Road | From B1098 Sixteen Foot Bank to A141 Isle of Ely Way | To be confirmed | To be confirmed |
Drainage projects
Planned works include repairs to existing drainage pipe and laying sections of new pipe, installing new drainage systems, gullies, and manholes.
2025-2026 programmes
Parish / Town | Road | Start date | Duration |
---|---|---|---|
Great Paxton | High Street | 7 July 2025 | 4 weeks. Work starts on High Street with traffic signals between 7am and 7pm. Work afterwards on River Lane will be carried out with reduced width restrictions during the day and road closure at night between 6pm and 6am. |
Great Gransden | East Street and Middle Street | 28 July 2025 | 9 weeks |
Stilton | North Street and High Street | 21 October 2025 | 18 weeks |
Chesterton | Oundle Road | To be confirmed | |
Yaxley | Broadway | To be confirmed | |
Stilton | North Street, High Street | 30 June 2025 | 8 weeks |
Somersham | Parkhall Road | To be confirmed | |
Fenstanton | Manor Drive, Hall Green Lane | To be confirmed | |
Needingworth | Hawkes Lane | To be confirmed | |
Fenstanton | Greenfields | To be confirmed |
2025-2026 design and investigation
Parish / Town | Road |
---|---|
Brampton | Buckden Road |
Hemingford Abbots | Various |
Huntingdon | St Johns Street |
Cyclical drainage work
Our cyclical drainage work is undertaken every other year. Work involves jetting, emptying, and cleaning all gullies and drains.
2025-2026 programmes
Parish / Town Road | Start Date | Duration | Actual completion date |
---|---|---|---|
Holme | 28 July 2025 | 1.5 days | |
Glatton | 30 July 2025 | 1 day | |
Connington | 30 July 2025 | 1 day | |
Sawtry | 31 July 2025 | 20.5 days | |
Woodwalton | 29 August 2025 | 1 day | |
Great Gidding | 29 August 2025 | 1 day | |
Hamerton and Steeple Gidding | 2 September 2025 | 0.5 days | |
Little Gidding | 1 September 2025 | 0.5 days | |
Winwick | 2 September 2025 | 0.5 days | |
Old Weston | 3 September 2025 | 1 day | |
Brington and Molesworth | 4 September 2025 | 1 day | |
Bythorn and Keyston | 5 September 2025 | 0.5 days | |
Catworth | 8 September 2025 | 1 day | |
Spaldwick | 9 September 2025 | 1.5 days | |
Ellington | 10 September 2025 | 1.5 days | |
Stow Longa | 11 September 2025 | 0.5 days | |
Covington | To be confirmed | ||
Tilbrook | To be confirmed | ||
Kimbolton | To be confirmed | ||
Grafham | To be confirmed | ||
Perry East and West | To be confirmed | ||
Buckden | To be confirmed | ||
Offord Cluny | To be confirmed | ||
Offord D'Arcy | To be confirmed | ||
Southoe | To be confirmed | ||
Great Paxton | To be confirmed | ||
Little Paxton | To be confirmed | ||
Hail Weston | To be confirmed | ||
Great Staughton | To be confirmed | ||
Diddington | To be confirmed | ||
St Neots | To be confirmed | ||
Alconbury Weston | To be confirmed | ||
Alconbury | To be confirmed | ||
Abbots Ripton | To be confirmed | ||
Broughton | To be confirmed | ||
Kings Ripton | To be confirmed | ||
Upton | To be confirmed | ||
Coppingford Road | To be confirmed | ||
The Stukeleys | To be confirmed | ||
Brampton | To be confirmed | ||
Huntingdon | To be confirmed |
Drainage grips
We make cuts into roadside verges so surface water can run off the road into a ditch. The cuts are called drainage grips.
2025-2026 programme
Parish / Town | Road | Extent of work | Start date | Actual completion date |
---|---|---|---|---|
Ramsey St Mary | B1040 | From Ponders Bridge to Huntingdon Road | To be confirmed | To be confirmed |
Godmanchester | Silver Street | From number 40 to playground | To be confirmed | To be confirmed |
Abbotsley | Pitsdean Road | From Blacksmiths Lane to speed limit | To be confirmed | To be confirmed |
Drainage projects
Planned works include repairs to existing drainage pipe and laying sections of new pipe. Plus installing new drainage systems, gullies, and manholes.
2025-2026 programmes
Parish / Town | Road | Start date | Duration |
---|---|---|---|
Linton | High Street | To be confirmed | 3 weeks |
Linton | Lamb Fair Court | To be confirmed |
2025-2026 design and investigation
Parish / Town | Road |
---|---|
Fulbourn | Station Road |
Great Wilbraham | Church Street |
Little Wilbraham | High Street |
Waterbeach | Chapel Street |
Cyclical drainage work
Our cyclical drainage work is undertaken every other year. Work involves jetting, emptying, and cleaning all gullies and drains.
2025-2026 programme
Parish / Town Road | Start Date | Duration | Actual completion date |
---|---|---|---|
Teversham | 28 April 2025 | 4 days | 1 May 2025 |
Little Wilbraham | 1 May 2025 | 0.5 days | 1 May 2025 |
Great Wilbraham | 2 May 2025 | 1.5 days | 5 May 2025 |
Fulbourn | 5 May 2025 | 6 days | 12 May 2025 |
Weston Colville | 13 May 2025 | 1 day | 13 May 2025 |
Carlton | 13 May 2025 | 1 day | 14 May 2025 |
West Wratting | 14 May 2025 | 0.5 days | 14 May 2025 |
Balsham | 15 May 2025 | 3 days | 19 May 2025 |
West Wickham and Streetly End | 20 May 2025 | 1 day | 20 May 2025 |
Hildersham | 20 May 2025 | 0.5 days | 20 May 2025 |
Linton | 21 May 2025 | 5 days | 27 May 2025 |
Horseheath and Cardinals Green | 28 May 2025 | 1 days | 28 May 2025 |
Bartlow | 28 May 2025 | 0.5 days | 28 May 2025 |
Shudy Camps | 29 May 2025 | 0.5 days | 29 May 2025 |
Castle Camps | 29 May 2025 | 0.5 days | 29 May 2025 |
Willingham | 30 May 2025 | 6 days | |
Rampton | 6 June 2025 | 1 day | |
Cottenham | 9 June 2025 | 6.5 days | |
Longstanton | 17 June 2025 | 8.5 days | |
Oakington and Westwick | 30 June 2025 | 3.5 days | |
Histon | 3 July 2025 | 6 days | |
Impington | 11 July 2025 | 7.5 days | |
Girton | 22 July 2025 | 4.5 days | |
Croxton | 28 July 2025 | 2 days | |
Eltisley | 28 July 2025 | 1.1 days | |
Caxton | 29 July 2025 | 2.5 days | |
Cambourne | 31 July 2025 | 12.5 days | |
Little Gransden | 19 August 2025 | 0.5 days | |
Longstowe | 19 August 2025 | 1 day | |
Gamlingay | 21 August 2025 | 6 days | |
Hatley St George and East Hatley | 29 August 2025 | 0.5 days | |
Croyden | 29 August 2025 | 0.5 days | |
Arrington | 29 August 2025 | 1 day | |
Tadlow | 1 September 2025 | 2 days | |
Shingay Cum Wendy | 2 September 2025 | 0.5 days | |
Guilden Morden | 2 September 2025 | 1.5 days | |
Steeple Morden | 4 September 2025 | 1.5 days | |
Abington Piggots | 5 September 2025 | 0.5 days | |
Litlington | 5 September 2025 | 1.5 days | |
Bassingbourn | 8 September 2025 | 4.5 days | |
Over | To be confirmed | ||
Fen Drayton | To be confirmed | ||
Swavesey | To be confirmed | ||
Connington | To be confirmed | ||
Boxworth | To be confirmed | ||
Lolworth | To be confirmed | ||
Graveley | To be confirmed | ||
Papworth St Agnes | To be confirmed | ||
Elsworth | To be confirmed | ||
Knapwell | To be confirmed | ||
Bar Hill | To be confirmed | ||
Dry Drayton | To be confirmed | ||
Madingley | To be confirmed | ||
Papworth Everard | To be confirmed |
Drainage grips
We make cuts into roadside verges so surface water can run off the road into a ditch. The cuts are called drainage grips.
2025-2026 programme
Parish / Town | Road | Extent of work | Start date | Actual completion date |
---|---|---|---|---|
B1052 Linton | Balsham Road | From Linton 30mph to Balsham 30mph | To be confirmed | To be confirmed |
Balsham | West Wickham Road | From Balsham 30mph to Horseheath 30mph | To be confirmed | To be confirmed |
West Wickham | Skippers Lane | From boundary to the common | To be confirmed | To be confirmed |
West Wratting | Six Mile Bottom | From Honey Hill to London Road | To be confirmed | To be confirmed |
Shudy Camps | Mill Green | From Horseheath Green to Nosterfield End | To be confirmed | To be confirmed |
Castle Camps | Bartlow Road | From Castle Camps 30mph to Bartlow 30mph | To be confirmed | To be confirmed |
Bartlow | Dean Road | From Bartlow 30mph to West Wickham road cross roads | To be confirmed | To be confirmed |
A1307 | A1307 | From Suffolk boundary to Cambridge Hinton Way roundabout | To be confirmed | To be confirmed |
Foxton | Fowlmere Road | From Cambridge road to Foxton village | To be confirmed | To be confirmed |
Barrington | Foxton Road | From Barrington 30mph to A10 | To be confirmed | To be confirmed |
B1368 | Barley | From county boundary to A10 | To be confirmed | To be confirmed |
Foxton | Shepreth Road | From 30mph to A10 junction | To be confirmed | To be confirmed |
Haslingfield | Barton Road | From Haslingfield 30mph to A603 Barton | To be confirmed | To be confirmed |
Swavesey | Fen Drayton Road | From Gibraltar lane to Rose and Crown Road | To be confirmed | To be confirmed |
Swavesey | Ramper Road | From Boxworth end to B1050 | To be confirmed | To be confirmed |
Fulbourn | Shelford Road | From 30mph to junction with Cherry Hinton Road | To be confirmed | To be confirmed |
Newton | High Road | Full length | To be confirmed | To be confirmed |
Cottenham | Oakington road | From orchard close to Guided bus | To be confirmed | To be confirmed |
Roadwork and traffic information
Our interactive map gives you more detail on the latest roadworks, road closures and diversions. Works listed on this page are included.
Visit our road and traffic information page to access the map and instructions on how to use. Details of upcoming roadworks in PDF format are also provided.
The map uses data from Causeway one.network. Enter your road name and see the types of work happening today or in the next two weeks, three or twelve months.
You can also follow us on X (formerly Twitter) for updates on where we are working - @Cambs_Traffic
Can't find what you are looking for?
If you are unable to find a scheme on this page, it may be part of our reactive or cyclical maintenance programmes.
These works are more area based and include gully cleansing, road patching and public rights of way maintenance.
You can find out more about the county-wide road resurfacing programme on our Road improvements page.
FAQ
Please read through our frequently asked questions. If you are unable to find the answer please contact us.
The work area is the section of the road where our operatives will be working. The road closure area often extends beyond this to manage through traffic and divert it on to an alternative route. This helps us do the work quickly and efficiently, while keeping residents, road users and the workforce safe.
If you receive information notifying you about a road closure, we will include a map which indicates both the work and road closure areas if these are different.
As the work involves heavy plant and equipment, we cannot guarantee you will be able to access your property without having to wait or access via the other end of the works.
If you normally drive into or out of the work area during the hours when the closure is in place, we may ask you to please make alternative arrangements.
We will often phase works to try to reduce the disruption this can cause, and the site team will be available to communicate with residents and businesses regarding this.
We will always maintain access to properties if it is safe to do so. Delays will sometimes be unavoidable when we must move machinery or equipment out of the way. We thank you for your patience and cooperation while this is done.
Work is phased to allow property access from at least one end of the road. Access may differ, depending on where we are working.
We place advance warning signs at the starting points of our works at least 14 days before the work starts.
We will inform residents and businesses which are located with the area of work, via letter or leaflet drop, at least 14 days in advance of work starting, wherever possible.
We try to keep noise to a minimum, and plan noisier working activities for earlier on in shifts where we are working at night in residential areas. However, the work is being delivered using heavy plant and machinery and this will cause noise and disruption whilst the work is on site, especially where we are working overnight. To try to limit this we:
- Consider alternative ways of working, for example during the day, instead of night, when working in residential areas at the weekend.
- Working reduced hours overnight. This approach often means a longer delivery programme, whereas working longer shifts will result in the work being completed quicker.
- Working during the day whenever we can to reduce costs and disruption to residents during unsociable hours.
Contact
To report an issue with a drain or gully, please visit our report a highways fault page.
If you have any queries or require any additional information please email: highways@cambridgeshire.gov.uk
Capital maintenance programme
For more information on the workstreams covered please visit our capital maintenance programme page.
How we are improving highways maintenance
Over the past two years, we have made the biggest investment in the highways network in over a decade, and it is important to show you where your money is spent.
Visit how we are improving highways maintenance. This page outlines our priorities, what improvements were made in 2024/25, and funding allocation for 2025/26.