20mph Delivery Programme Update

Delivery Programme Banner (002)

This page allows you to check the delivery progress of your 20mph scheme.

The updates are tracked from approval through to completion. This page is updated monthly by officers.

This is an example of a design and sign drawing for Meldreth Parish Council, designed by our in-house design team.

20mph parish design example
20mph parish design example

Progress updates

There are six stages to completion.

2023/2024 schemes

Location 20mph Installation Area Project Stage Project Update (as at 8 October 2025)

Cottenham

Village wide

3 - Formal consultation

TRO consultation has closed and CCC officers have reviewed responses ahead of the report being published. The project shall be considered in the January 2026 Highways & Transportation Committee meeting.

Linton

Village wide

4 - Pre construction

Formal consultation has completed. The project was requested to be paused previously. Now, the project is within the pricing stage. We are awaiting confirmation of costs before ordering the works for delivery.

Meldreth

Majority of village

6 - Final account

Works operationally completed.

Orwell

Village wide

6 - Final account

Works operationally completed.

Great Wilbraham

Village wide

6 - Final account

Works operationally completed.

Great Staughton

Majority of village

6 - Final account

Works operationally completed.

Great Abington

Part of village including Linton and High Street

6 - Final account

Works operationally completed.

Fowlmere

Extending 20mph from entrance into village

6 - Final account

Works operationally completed.

Fulbourn

Majority of village

6 - Final account

Works operationally completed.

Harlton

Village wide

6 - Final account

Works operationally completed.

Wicken

Village wide

6 - Final account

Works operationally completed.

Burwell

Village wide

Parish have withdrawn application following informal consultation with residents.

Upwood and The Raveleys

Parish wide on all eligible 30mph roads

6 - Final account

Works operationally completed.

Elton

Majority of village

6 - Final account

Works operationally completed.

Houghton and Wyton

Village wide

6 - Final account

Works operationally completed.

Hilton

Village wide

4 - Pre Construction

Delegated decision approval 15 September 2025. Currently working through review of construction cost estimates, to then raise the work order for delivery.

Whittlesford

Village wide

5 - Delivery

Works operationally completed.

Girton

Extend the current 20mph zone to remainder of village.

6 - Final account

Works operationally completed.

Willingham

Village wide

6 - Final account

Works operationally completed.

Oakington and Westwick

Extend the current 20 mph zone to include Westwick.

6 - Final account

Works operationally completed.

2024/2025 schemes

Waterbeach

Village wide

1 - Detailed design

Draft detailed design in progress, next step informal consultation with Parish or Town Council before progression to formal consultation for the approved plans.

Stow cum Quy

Village wide

4 - Pre Construction

Proposal was accepted through formal consultation. Now, the project is within the pricing stage. We are awaiting confirmation of costs before proceeding with making works orders and booking delivery dates.

Elm

Village wide

2 - Consultation stage

Detailed design is finalising. The next step is to progress to formal consultation.

Bottisham

Village wide

3 - Formal consultation

Formal consultation was published on 30 July and closed on the 20 August 2025. The democratic delegated decision process to occur to review and determine the next steps for the project.

Little Paxton

Village wide

3 - Formal consultation

Formal consultation is now live. It is advertised from 8 October 2025, closing 30 October 2025. See here: Permanent Traffic Regulation Orders | Cambridgeshire County Council

Earith

Majority of village

3 - Formal consultation

This project is within formal consultation stage, following the acceptance of the detailed design drawings.

Swavesey

Majority of village

3 - Formal consultation

This project is within formal consultation stage, following the acceptance of the detailed design drawings. We await the advertisement dates (expected to occur from November 2025).

Steeple Morden

Central area of village

4 - Pre Construction

Formal consultation closed with no objections. Currently working to review costs and raise order to operationally deliver the project.