Skip to main content

20mph delivery programme update

Delivery Programme Banner (002)

This page allows you to check the delivery progress of your 20mph scheme.

The updates are tracked from approval through to completion. This page is updated monthly by officers.

This is an example of a design and sign drawing for Meldreth Parish Council, designed by our in-house design team.

20mph parish design example
20mph parish design example

Progress updates

There are six stages to completion.

2023/2024 schemes

Location 20mph Installation area Project stage Project update (as at 4 June 2026)

Cottenham

Village wide

5 - Delivery

Works operationally completed.

Linton

Village wide

5 - Delivery

Works ordered, provisional start date week commencing 15 June 2026.

Meldreth

Majority of village

6 - Final account

Works operationally completed.

Orwell

Village wide

6 - Final account

Works operationally completed.

Great Wilbraham

Village wide

6 - Final account

Works operationally completed.

Great Staughton

Majority of village

6 - Final account

Works operationally completed.

Great Abington

Part of village including Linton and High Street

6 - Final account

Works operationally completed.

Fowlmere

Extending 20mph from entrance into village

6 - Final account

Works operationally completed.

Fulbourn

Majority of village

6 - Final account

Works operationally completed.

Harlton

Village wide

6 - Final account

Works operationally completed.

Wicken

Village wide

6 - Final account

Works operationally completed.

Burwell

Village wide

Application withdrawn following Parish Council informal consultation with residents.

Upwood and The Raveleys

Parish wide on all eligible 30mph roads

6 - Final account

Works operationally completed.

Elton

Majority of village

6 - Final account

Works operationally completed.

Houghton and Wyton

Village wide

6 - Final account

Works operationally completed.

Hilton

Village wide

5 - Delivery

Scheme at delivery stage. All on track to be installed and enforceable by the end of March 2026.

Whittlesford

Village wide

5 - Delivery

Works operationally completed.

Girton

Extend the current 20mph zone to remainder of village.

6 - Final account

Works operationally completed.

Willingham

Village wide

6 - Final account

Works operationally completed.

Oakington and Westwick

Extend the current 20 mph zone to include Westwick.

6 - Final account

Works operationally completed.

2024/2025 schemes

Location 20mph Installation Area Project Stage Project Update (as at 4 June 2026)

Waterbeach

Village wide

2 - Consultation stage

Detailed design in progress. CC to undertake informal consultation with Parish Council.

Stow cum Quy

Village wide

5 - Delivery

Works order raised for operational delivery. Delivery expected 15 - 17 July 2026.

Elm

Village wide

3 - Formal consultation

Formal consultation closed, objections received progressing to Delegated Decision 5 June 2026.

Bottisham

Village wide

5 - Delivery

Formal consultation complete. Order raised June 2026 and awaiting provisional delivery date for summer 2026. 

Little Paxton

Village wide

6 - Final account

Works operationally completed.

Earith

Majority of village

5 - Delivery

Works ordered, awaiting operational delivery dates confirmation. Delivery expected 15 - 17 July 2026.

Swavesey

Majority of village

4 - Pre Construction

Formal consultation complete. Reviewing design for ordering alongside the S106 scheme.

Steeple Morden

Central area of village

6 - Final account

Works operationally completed.

 2025/2026 schemes

Location 20mph Installation Area Project Stage Project Update (as at 4 June 2026)

Landbeach

Village wide

1 - Detailed design

Project scope agreed with the Parish for the for the proposed project. Next steps are: Detailed design; then project consultation to follow.
 Harston

Village wide

1 - Detailed design

Project scope agreed with parish. Next steps are: Detailed design to be drafted, and project consultation to follow.
 Madingley  Village wide 1 - Detailed design Project scope agreed with parish. Next steps are: Detailed design to be drafted, and project consultation to follow.
 Barrington  Village wide 1 - Detailed design  Project scope agreed with parish. Next steps are: Detailed design to be drafted, and project consultation to follow.
 Offords  Village wide 1 - Detailed design  Project scope aligned with application. Next step is to complete detailed design; and then prepare for formal consultation of proposal.
 Comberton  Village wide 1 - Detailed design  Project scope agreed with parish.  Next steps are: Detailed design to be drafted, and project consultation to follow.
 Newton  Village wide 1 - Detailed design  Project scope agreed with parish.  Next steps are: Detailed design to be drafted, and project consultation to follow.
 Waresley  Village wide 1 - Detailed design  Project scope is aligned with application. Next step is to complete detailed design; and then prepare for formal consultation of proposal.
 Milton  Village wide 1 - Detailed design  Awarded funding in October 2025 CCC Highways and Transportation Committee meeting. 
 Wilburton  Village wide 3 - Formal Consultation Draft design agreed with Parish. Formal consultation complete and approved at Delegated Decision, reviewing design for ordering June 2026.
 Sutton  Village wide 1 - Detailed design  Awarded funding in October 2025 CCC Highways and Transportation Committee meeting.