Skip to main content

20mph delivery programme update

Delivery Programme Banner (002)

This page allows you to check the delivery progress of your 20mph scheme.

The updates are tracked from approval through to completion. This page is updated monthly by officers.

This is an example of a design and sign drawing for Meldreth Parish Council, designed by our in-house design team.

20mph parish design example
20mph parish design example

Progress updates

There are six stages to completion.

2023/2024 schemes

Location 20mph Installation area Project stage Project update (as at 4 September 2026)
Cottenham Village wide 6 - Final account Works operationally completed.
Linton Village wide 6 - Final account Works operationally completed.
Meldreth Majority of village 6 - Final account Works operationally completed.
Orwell Village wide 6 - Final account Works operationally completed.
Great Wilbraham Village wide 6 - Final account Works operationally completed.
Great Staughton Majority of village 6 - Final account Works operationally completed.
Great Abington Part of village including Linton & Highstreet 6 - Final account Works operationally completed.
Fowlmere Extending 20mph from entrance into village 6 - Final account Works operationally completed.
Fulbourn Majority of village 6 - Final account Works operationally completed.
Harlton Village wide 6 - Final account Works operationally completed.
Wicken Village wide 6 - Final account Works operationally completed.
Burwell Village wide   Application withdrawn following Parish Council informal consultation with residents.
Upwood and The Raveleys Parish wide on all eligible 30mph roads 6 - Final account Works operationally completed.
Elton Majority of village 6 - Final account Works operationally completed.
Houghton and Wyton Village wide 6 - Final account Works operationally completed.
Hilton Village wide 6 - Final account Works operationally completed.
Whittlesford Village wide 5 - Delivery Works operationally completed.
Girton Extend the current 20mph zone to remainder of village. 6 - Final account Works operationally completed.
Willingham Village wide 6 - Final account Works operationally completed.
Oakington & Westwick Extend the current 20 mph zone to include Westwick. 6 - Final account Works operationally completed.

2024/2025 schemes

Location 20mph Installation Area Project Stage Project update (as at 4 September 2026)
Waterbeach Village wide 2 - Consultation stage Detailed design has been shared and agreed. Informal consultation currently taking place to end of September 2026.
Stow cum Quy Village wide 6 - Final account Works operationally completed.
Elm Village wide 4 - Pre construction Scheme at delivery stage. Awaiting programme date for September/October 2026 delivery.
Bottisham Village wide 6 - Final account Works operationally completed.
Little Paxton Village wide 6 - Final account Works operationally completed.
Earith Majority of village 6 - Final account Works operationally completed.
Swavesey Majority of village 4 - Pre construction Scheme at delivery stage. Awaiting programme date for November 2026 delivery.
Steeple Morden Central area of village 6 - Final account Works operationally completed.

 2025/2026 schemes

Location 20mph Installation Area Project Stage Project update (as at 4 September 2026)
Landbeach Village wide 1 - Detailed design Project scope agreed with the Parish for the for the proposed project. Next steps are: Detailed design; then project consultation to follow.
Harston Village wide 1 - Detailed design Project scope agreed with parish. Next steps are: Detailed design to be drafted, and project consultation to follow.
Madingley Village wide 1 - Detailed design Project scope agreed with parish. Next steps are: Detailed design to be drafted, and project consultation to follow.
Barrington Village wide 1 - Detailed design Project scope agreed with parish. Next steps are: Detailed design to be drafted, and project consultation to follow.
Offords Village wide 1 - Detailed design Project scope aligned with application. Next step is to complete detailed design; and then prepare for formal consultation of proposal.
Comberton Village wide 1 - Detailed design Project scope agreed with parish. Next steps are: Detailed design to be drafted, and project consultation to follow.
Newton Multiple roads 1 - Detailed design Project scope agreed with parish. Next steps are: Detailed design to be drafted, and project consultation to follow.
Waresley Multiple roads 2 - Consultation stage Preliminary design is complete. Next step is to gain parish approval of design; and then prepare for formal consultation of proposal.
Milton Village wide 1 - Detailed design Awarded funding in October 2025 CCC Highways & Transportation Committee meeting. The scope of the intended project is agreed with applicant. Awaiting designer allocation.
Wilburton Village wide 4 - Pre construction Draft design agreed with Parish. Formal consultation complete and approved at Delegated Decision. Project to be ordered for programming. 
Sutton Multiple roads 3 - Formal consultation Design approved by the Parish. Next step publication of formal notice.