Skip to main content

20mph Delivery Programme Update

Delivery Programme Banner (002)

This page allows you to check the delivery progress of your 20mph scheme.

The updates are tracked from approval through to completion. This page is updated monthly by officers.

This is an example of a design and sign drawing for Meldreth Parish Council, designed by our in-house design team.

20mph parish design example
20mph parish design example

Progress updates

There are six stages to completion.

2023/2024 schemes

Location 20mph Installation area Project stage Project update (as at 5 January 2026)

Cottenham

Village wide

3 - Formal consultation

Project preparing for delivery following approval to proceed at January 2026 Highways and Transportation committee meeting. 

Linton

Village wide

4 - Pre construction

Works ordered, awaiting operational delivery dates.

Meldreth

Majority of village

6 - Final account

Works operationally completed.

Orwell

Village wide

6 - Final account

Works operationally completed.

Great Wilbraham

Village wide

6 - Final account

Works operationally completed.

Great Staughton

Majority of village

6 - Final account

Works operationally completed.

Great Abington

Part of village including Linton and High Street

6 - Final account

Works operationally completed.

Fowlmere

Extending 20mph from entrance into village

6 - Final account

Works operationally completed.

Fulbourn

Majority of village

6 - Final account

Works operationally completed.

Harlton

Village wide

6 - Final account

Works operationally completed.

Wicken

Village wide

6 - Final account

Works operationally completed.

Burwell

Village wide

Application withdrawn following Parish Council informal consultation with residents.

Upwood and The Raveleys

Parish wide on all eligible 30mph roads

6 - Final account

Works operationally completed.

Elton

Majority of village

6 - Final account

Works operationally completed.

Houghton and Wyton

Village wide

6 - Final account

Works operationally completed.

Hilton

Village wide

5 - Delivery

Works ordered, awaiting operational delivery dates.

Whittlesford

Village wide

5 - Delivery

Works operationally completed.

Girton

Extend the current 20mph zone to remainder of village.

6 - Final account

Works operationally completed.

Willingham

Village wide

6 - Final account

Works operationally completed.

Oakington and Westwick

Extend the current 20 mph zone to include Westwick.

6 - Final account

Works operationally completed.

2024/2025 schemes

Location 20mph Installation Area Project Stage Project Update (as at 28 November 2025)

Waterbeach

Village wide

1 - Detailed design

Detailed design in progress. Support to Parish Council to occur with informal consultation.

Stow cum Quy

Village wide

4 - Pre construction

Works order raised for operational delivery. Awaiting delivery dates from contractor.

Elm

Village wide

3 - Formal consultation

Design approved, consultation is currently open for comments until 11 February 2026.

Bottisham

Village wide

4 - Pre construction

Formal consultation complete. Currently working to review costs and raise the work order.

Little Paxton

Village wide

5 - Delivery

Works ordered, awaiting operational delivery dates.

Earith

Majority of village

5 - Delivery

Works ordered, awaiting operational delivery dates.

Swavesey

Majority of village

3 - Formal consultation

Formal consultation closed, objections received progressing to Delegated Decision late February 2026.

Steeple Morden

Central area of village

5 - Delivery

Scheme at delivery stage. All on track to be installed and enforceable by the 20th February 2026.

 2025/2026 schemes

Location 20mph Installation Area Project Stage Project Update (as at 28 November 2025)

Landbeach

Village wide

1 - Detailed design

Awarded funding in October 2025 CCC Highways and Transportation Committee meeting. 
 Harston

Village wide

1 - Detailed design

Awarded funding in October 2025 CCC Highways and Transportation Committee meeting. 
 Madingley  Village wide 1 - Detailed design Awarded funding in October 2025 CCC Highways and Transportation Committee meeting. 
 Barrington  Village wide 1 - Detailed design  Awarded funding in October 2025 CCC Highways and Transportation Committee meeting. 
 Offords  Village wide 1 - Detailed design  Awarded funding in October 2025 CCC Highways and Transportation Committee meeting.
 Comberton  Village wide 1 - Detailed design  Awarded funding in October 2025 CCC Highways and Transportation Committee meeting.
 Newton  Village wide 1 - Detailed design  Awarded funding in October 2025 CCC Highways and Transportation Committee meeting.
 Waresley  Village wide 1 - Detailed design  Awarded funding in October 2025 CCC Highways and Transportation Committee meeting.
 Milton  Village wide 1 - Detailed design  Awarded funding in October 2025 CCC Highways and Transportation Committee meeting.
 Wilburton  Village wide 1 - Detailed design  Awarded funding in October 2025 CCC Highways and Transportation Committee meeting.
 Sutton  Village wide 1 - Detailed design  Awarded funding in October 2025 CCC Highways and Transportation Committee meeting.