Skip to main content

20mph Delivery Programme Update

Delivery Programme Banner (002)

This page allows you to check the delivery progress of your 20mph scheme.

The updates are tracked from approval through to completion. This page is updated monthly by officers.

This is an example of a design and sign drawing for Meldreth Parish Council, designed by our in-house design team.

20mph parish design example
20mph parish design example

Progress updates

There are six stages to completion.

2023/2024 schemes

Location 20mph Installation Area Project Stage Project Update (as at 28 January 2025)
Cottenham Villagewide 3 - Formal consultation TRO consultation has closed and currently CCC officers are reviewing responses ahead of the report being drafted.
Linton Villagewide 4 - Pre construction Formal consultation complete. Currently working to review costs and raise the work order.
Meldreth Majority of village 4 - Pre construction Formal consultation complete. Currently working to review costs and raise the work order.
Orwell Villagewide 6 - Final account Works complete.
Great Wilbraham Villagewide 5 - Delivery Scheme at delivery stage. All on track to be installed and enforceable in the upcoming months.
Great Staughton Majority of village 6 - Final account Works complete.
Great Abington Part of village including Linton and High Street 6 - Final account Works complete.
Fowlmere Extending 20mph from entrance into village 6 - Final account Works complete.
Fulbourn Majority of village 5 - Delivery Scheme at delivery stage. All on track to be installed and enforceable in the upcoming months.
Harlton Villagewide 6 - Final account Works complete.
Wicken Villagewide 5 - Delivery Scheme at delivery stage. All on track to be installed and enforceable by the Spring 2025.
Burwell Villagewide   Parish have withdrew application following informal consultation with residents.
Upwood and The Raveleys Parishwide on all eligible 30mph roads 5 - Delivery Scheme at delivery stage. All on track to be installed and enforceable by the Spring 2025.
Elton Majority of village 6 - Final account Works complete.
Houghton and Wyton Villagewide 4 - Pre construction Formal consultation complete. Currently working to review costs and raise the work order.
Hilton Villagewide 3 - Formal consultation Draft design agreed with Parish or Town Council. Next step publication of formal notice
Whittlesford Villagewide 4 - Pre construction Formal consultation complete. Currently working to review costs and raise the work order.
Girton Extend the current 20mph zone to remainder of village. 4 - Pre construction Scheme approved at Delegated Decision January 2025. Scheme to progress to delivery stage.
Willingham Villagewide 5 - Delivery Scheme at delivery stage. All on track to be installed and enforceable by the Spring 2025.
Oakington & Westwick Extend the current 20 mph zone to include Westwick. 4 - Pre construction Scheme approved at Delegated Decision January 2025. Scheme to progress to delivery stage. 

2024/2025 schemes

Waterbeach Village wide 1 - Detailed Design Draft detailed design in progress, next step informal consultation with Parish or Town Council.
Stow cum Quy Village wide 1 - Detailed Design Draft detailed design in progress, next step informal consultation with Parish or Town Council.
Elm Village wide 1 - Detailed Design Draft detailed design in progress, next step informal consultation with Parish or Town Council.
Bottisham Village wide 1 - Detailed Design Draft detailed design in progress, next step informal consultation with Parish or Town Council.
Little Paxton village wide 1 - Detailed Design Draft detailed design in progress, next step informal consultation with Parish or Town Council.
Earith Majority of village 1 - Detailed Design Draft detailed design in progress, next step informal consultation with Parish or Town Council.
Swavesey Majority of village 1 - Detailed Design Draft detailed design in progress, next step informal consultation with Parish or Town Council.
Steeple Morden Central area of village 1 - Detailed Design Draft detailed design in progress, next step informal consultation with Parish or Town Council.