
This page allows you to check the delivery progress of your 20mph scheme.
The updates are tracked from approval through to completion. This page is updated monthly by officers.
This is an example of a design and sign drawing for Meldreth Parish Council, designed by our in-house design team.
Progress updates
There are six stages to completion.
2023/2024 schemes
| Location | 20mph Installation area | Project stage | Project update (as at 11 March 2026) |
|
Cottenham |
Village wide |
4 - Pre Construction |
Project preparing for delivery following approval to proceed at January 2026 Highways and Transportation committee meeting. |
|
Linton |
Village wide |
4 - Pre construction |
Works ordered, awaiting operational delivery dates. |
|
Meldreth |
Majority of village |
6 - Final account |
Works operationally completed. |
|
Orwell |
Village wide |
6 - Final account |
Works operationally completed. |
|
Great Wilbraham |
Village wide |
6 - Final account |
Works operationally completed. |
|
Great Staughton |
Majority of village |
6 - Final account |
Works operationally completed. |
|
Great Abington |
Part of village including Linton and High Street |
6 - Final account |
Works operationally completed. |
|
Fowlmere |
Extending 20mph from entrance into village |
6 - Final account |
Works operationally completed. |
|
Fulbourn |
Majority of village |
6 - Final account |
Works operationally completed. |
|
Harlton |
Village wide |
6 - Final account |
Works operationally completed. |
|
Wicken |
Village wide |
6 - Final account |
Works operationally completed. |
|
Burwell |
Village wide |
Application withdrawn following Parish Council informal consultation with residents. |
|
|
Upwood and The Raveleys |
Parish wide on all eligible 30mph roads |
6 - Final account |
Works operationally completed. |
|
Elton |
Majority of village |
6 - Final account |
Works operationally completed. |
|
Houghton and Wyton |
Village wide |
6 - Final account |
Works operationally completed. |
|
Hilton |
Village wide |
5 - Delivery |
Scheme at delivery stage. All on track to be installed and enforceable by the end of March 2026. |
|
Whittlesford |
Village wide |
5 - Delivery |
Works operationally completed. |
|
Girton |
Extend the current 20mph zone to remainder of village. |
6 - Final account |
Works operationally completed. |
|
Willingham |
Village wide |
6 - Final account |
Works operationally completed. |
|
Oakington and Westwick |
Extend the current 20 mph zone to include Westwick. |
6 - Final account |
Works operationally completed. |
2024/2025 schemes
| Location | 20mph Installation Area | Project Stage | Project Update (as at 11 March 2026) |
|
Waterbeach |
Village wide |
2 - Consultation Stage |
Detailed design in progress. Support to Parish Council to occur with informal consultation. |
|
Stow cum Quy |
Village wide |
4 - Pre construction |
Works order raised for operational delivery. Awaiting delivery dates from contractor. |
|
Elm |
Village wide |
3 - Formal consultation |
Formal consultation closed, objections received progressing to Delegated Decision late March 2026. |
|
Bottisham |
Village wide |
4 - Pre construction |
Formal consultation complete. Currently working to review costs and raise the work order. |
|
Little Paxton |
Village wide |
5 - Delivery |
Works ordered, awaiting operational delivery dates. |
|
Earith |
Majority of village |
5 - Delivery |
Works ordered, awaiting operational delivery dates. |
|
Swavesey |
Majority of village |
4 - Pre Construction |
Formal consultation complete. Currently working to review costs and raise the work order. |
|
Steeple Morden |
Central area of village |
5 - Delivery |
Scheme at delivery stage. All on track to be installed and enforceable by the 20th March 2026. |
2025/2026 schemes
| Location | 20mph Installation Area | Project Stage | Project Update (as at 11 March 2026) |
|
Landbeach |
Village wide |
1 - Detailed design |
Awarded funding in October 2025 CCC Highways and Transportation Committee meeting. |
| Harston |
Village wide |
1 - Detailed design |
Awarded funding in October 2025 CCC Highways and Transportation Committee meeting. |
| Madingley | Village wide | 1 - Detailed design | Awarded funding in October 2025 CCC Highways and Transportation Committee meeting. |
| Barrington | Village wide | 1 - Detailed design | Awarded funding in October 2025 CCC Highways and Transportation Committee meeting. |
| Offords | Village wide | 1 - Detailed design | Awarded funding in October 2025 CCC Highways and Transportation Committee meeting. |
| Comberton | Village wide | 1 - Detailed design | Awarded funding in October 2025 CCC Highways and Transportation Committee meeting. |
| Newton | Village wide | 1 - Detailed design | Awarded funding in October 2025 CCC Highways and Transportation Committee meeting. |
| Waresley | Village wide | 1 - Detailed design | Awarded funding in October 2025 CCC Highways and Transportation Committee meeting. |
| Milton | Village wide | 1 - Detailed design | Awarded funding in October 2025 CCC Highways and Transportation Committee meeting. |
| Wilburton | Village wide | 3 - Formal Consultation | Draft design agreed with Parish. Next step publication of formal notice from 12/02/2026 to 05/03/2026. Awaiting outcome. |
| Sutton | Village wide | 1 - Detailed design | Awarded funding in October 2025 CCC Highways and Transportation Committee meeting. |