
This page allows you to check the delivery progress of your 20mph scheme.
The updates are tracked from approval through to completion. This page is updated monthly by officers.
This is an example of a design and sign drawing for Meldreth Parish Council, designed by our in-house design team.
Progress updates
There are six stages to completion.
2023/2024 schemes
| Location | 20mph Installation area | Project stage | Project update (as at 4 June 2026) |
|
Cottenham |
Village wide |
5 - Delivery |
Works operationally completed. |
|
Linton |
Village wide |
5 - Delivery |
Works ordered, provisional start date week commencing 15 June 2026. |
|
Meldreth |
Majority of village |
6 - Final account |
Works operationally completed. |
|
Orwell |
Village wide |
6 - Final account |
Works operationally completed. |
|
Great Wilbraham |
Village wide |
6 - Final account |
Works operationally completed. |
|
Great Staughton |
Majority of village |
6 - Final account |
Works operationally completed. |
|
Great Abington |
Part of village including Linton and High Street |
6 - Final account |
Works operationally completed. |
|
Fowlmere |
Extending 20mph from entrance into village |
6 - Final account |
Works operationally completed. |
|
Fulbourn |
Majority of village |
6 - Final account |
Works operationally completed. |
|
Harlton |
Village wide |
6 - Final account |
Works operationally completed. |
|
Wicken |
Village wide |
6 - Final account |
Works operationally completed. |
|
Burwell |
Village wide |
Application withdrawn following Parish Council informal consultation with residents. |
|
|
Upwood and The Raveleys |
Parish wide on all eligible 30mph roads |
6 - Final account |
Works operationally completed. |
|
Elton |
Majority of village |
6 - Final account |
Works operationally completed. |
|
Houghton and Wyton |
Village wide |
6 - Final account |
Works operationally completed. |
|
Hilton |
Village wide |
5 - Delivery |
Scheme at delivery stage. All on track to be installed and enforceable by the end of March 2026. |
|
Whittlesford |
Village wide |
5 - Delivery |
Works operationally completed. |
|
Girton |
Extend the current 20mph zone to remainder of village. |
6 - Final account |
Works operationally completed. |
|
Willingham |
Village wide |
6 - Final account |
Works operationally completed. |
|
Oakington and Westwick |
Extend the current 20 mph zone to include Westwick. |
6 - Final account |
Works operationally completed. |
2024/2025 schemes
| Location | 20mph Installation Area | Project Stage | Project Update (as at 4 June 2026) |
|
Waterbeach |
Village wide |
2 - Consultation stage |
Detailed design in progress. CC to undertake informal consultation with Parish Council. |
|
Stow cum Quy |
Village wide |
5 - Delivery |
Works order raised for operational delivery. Delivery expected 15 - 17 July 2026. |
|
Elm |
Village wide |
3 - Formal consultation |
Formal consultation closed, objections received progressing to Delegated Decision 5 June 2026. |
|
Bottisham |
Village wide |
5 - Delivery |
Formal consultation complete. Order raised June 2026 and awaiting provisional delivery date for summer 2026. |
|
Little Paxton |
Village wide |
6 - Final account |
Works operationally completed. |
|
Earith |
Majority of village |
5 - Delivery |
Works ordered, awaiting operational delivery dates confirmation. Delivery expected 15 - 17 July 2026. |
|
Swavesey |
Majority of village |
4 - Pre Construction |
Formal consultation complete. Reviewing design for ordering alongside the S106 scheme. |
|
Steeple Morden |
Central area of village |
6 - Final account |
Works operationally completed. |
2025/2026 schemes
| Location | 20mph Installation Area | Project Stage | Project Update (as at 4 June 2026) |
|
Landbeach |
Village wide |
1 - Detailed design |
Project scope agreed with the Parish for the for the proposed project. Next steps are: Detailed design; then project consultation to follow. |
| Harston |
Village wide |
1 - Detailed design |
Project scope agreed with parish. Next steps are: Detailed design to be drafted, and project consultation to follow. |
| Madingley | Village wide | 1 - Detailed design | Project scope agreed with parish. Next steps are: Detailed design to be drafted, and project consultation to follow. |
| Barrington | Village wide | 1 - Detailed design | Project scope agreed with parish. Next steps are: Detailed design to be drafted, and project consultation to follow. |
| Offords | Village wide | 1 - Detailed design | Project scope aligned with application. Next step is to complete detailed design; and then prepare for formal consultation of proposal. |
| Comberton | Village wide | 1 - Detailed design | Project scope agreed with parish. Next steps are: Detailed design to be drafted, and project consultation to follow. |
| Newton | Village wide | 1 - Detailed design | Project scope agreed with parish. Next steps are: Detailed design to be drafted, and project consultation to follow. |
| Waresley | Village wide | 1 - Detailed design | Project scope is aligned with application. Next step is to complete detailed design; and then prepare for formal consultation of proposal. |
| Milton | Village wide | 1 - Detailed design | Awarded funding in October 2025 CCC Highways and Transportation Committee meeting. |
| Wilburton | Village wide | 3 - Formal Consultation | Draft design agreed with Parish. Formal consultation complete and approved at Delegated Decision, reviewing design for ordering June 2026. |
| Sutton | Village wide | 1 - Detailed design | Awarded funding in October 2025 CCC Highways and Transportation Committee meeting. |