
This page allows you to check the delivery progress of your 20mph scheme.
The updates are tracked from approval through to completion. This page is updated monthly by officers.
This is an example of a design and sign drawing for Meldreth Parish Council, designed by our in-house design team.
Progress updates
There are six stages to completion.
2023/2024 schemes
| Location | 20mph Installation Area | Project Stage | Project Update (as at 8 October 2025) |
|
Cottenham |
Village wide |
3 - Formal consultation |
TRO consultation has closed and CCC officers have reviewed responses ahead of the report being published. The project shall be considered in the January 2026 Highways & Transportation Committee meeting. |
|
Linton |
Village wide |
4 - Pre construction |
Formal consultation has completed. The project was requested to be paused previously. Now, the project is within the pricing stage. We are awaiting confirmation of costs before ordering the works for delivery. |
|
Meldreth |
Majority of village |
6 - Final account |
Works operationally completed. |
|
Orwell |
Village wide |
6 - Final account |
Works operationally completed. |
|
Great Wilbraham |
Village wide |
6 - Final account |
Works operationally completed. |
|
Great Staughton |
Majority of village |
6 - Final account |
Works operationally completed. |
|
Great Abington |
Part of village including Linton and High Street |
6 - Final account |
Works operationally completed. |
|
Fowlmere |
Extending 20mph from entrance into village |
6 - Final account |
Works operationally completed. |
|
Fulbourn |
Majority of village |
6 - Final account |
Works operationally completed. |
|
Harlton |
Village wide |
6 - Final account |
Works operationally completed. |
|
Wicken |
Village wide |
6 - Final account |
Works operationally completed. |
|
Burwell |
Village wide |
Parish have withdrawn application following informal consultation with residents. |
|
|
Upwood and The Raveleys |
Parish wide on all eligible 30mph roads |
6 - Final account |
Works operationally completed. |
|
Elton |
Majority of village |
6 - Final account |
Works operationally completed. |
|
Houghton and Wyton |
Village wide |
6 - Final account |
Works operationally completed. |
|
Hilton |
Village wide |
4 - Pre Construction |
Delegated decision approval 15 September 2025. Currently working through review of construction cost estimates, to then raise the work order for delivery. |
|
Whittlesford |
Village wide |
5 - Delivery |
Works operationally completed. |
|
Girton |
Extend the current 20mph zone to remainder of village. |
6 - Final account |
Works operationally completed. |
|
Willingham |
Village wide |
6 - Final account |
Works operationally completed. |
|
Oakington and Westwick |
Extend the current 20 mph zone to include Westwick. |
6 - Final account |
Works operationally completed. |
2024/2025 schemes
|
Waterbeach |
Village wide |
1 - Detailed design |
Draft detailed design in progress, next step informal consultation with Parish or Town Council before progression to formal consultation for the approved plans. |
|
Stow cum Quy |
Village wide |
4 - Pre Construction |
Proposal was accepted through formal consultation. Now, the project is within the pricing stage. We are awaiting confirmation of costs before proceeding with making works orders and booking delivery dates. |
|
Elm |
Village wide |
2 - Consultation stage |
Detailed design is finalising. The next step is to progress to formal consultation. |
|
Bottisham |
Village wide |
3 - Formal consultation |
Formal consultation was published on 30 July and closed on the 20 August 2025. The democratic delegated decision process to occur to review and determine the next steps for the project. |
|
Little Paxton |
Village wide |
3 - Formal consultation |
Formal consultation is now live. It is advertised from 8 October 2025, closing 30 October 2025. See here: Permanent Traffic Regulation Orders | Cambridgeshire County Council |
|
Earith |
Majority of village |
3 - Formal consultation |
This project is within formal consultation stage, following the acceptance of the detailed design drawings. |
|
Swavesey |
Majority of village |
3 - Formal consultation |
This project is within formal consultation stage, following the acceptance of the detailed design drawings. We await the advertisement dates (expected to occur from November 2025). |
|
Steeple Morden |
Central area of village |
4 - Pre Construction |
Formal consultation closed with no objections. Currently working to review costs and raise order to operationally deliver the project. |