We maintain over 4,600 kilometres of road network across the county on behalf of our communities. This includes:
- 532 km of A-road network
- 578 km of B-road network
- 3,498 km of C and Unclassified Road network
- In 2023, 5.1 billion vehicle miles were travelled in Cambridgeshire, an increase of over half a billion vehicle miles in ten years.
- Over 40% of our network is built over peat soil which present unique challenges as it is structurally weak.

The information here provides details on the planned repairs to roads that we will be undertaking across the county.
The scale and type of work will vary depending on the individual scheme and the repair being undertaken.
Most work will be delivered under a full road closure. This will cause disruption to the road network whilst we are on site. We will keep disruption to a minimum and we appreciate your cooperation during these critical works.
As well as the large-scale work on roads, planned in advance, we also continually do reactive road repairs across the whole county. These include pothole repairs and patching work, which is carried out on defects that we spot through routine inspection or if an issue has been reported by a member of the public. This helps keep the highways network running smoothly.
Planned work by district
Updates are provided monthly by officers. Expand the district below to see when and where work will take place and road closures.
Whilst we aim to be as accurate as possible with the below times and dates, there are instances where these may change at short notice.
Large-scale road maintenance
Our large-scale road maintenance involves reconstruction to replace the top layers of the road and provide a stable support for vehicle movement. Works include, where needed, vegetation clearance, drainage, signage and road markings.
2025-2026 programmes
| Parish / Town | Road | Start date | Duration |
|---|---|---|---|
| Cambridge | Parker Street | 18 August 2025 | Completed |
| Cambridge | Jesus Lane (Phase 1) | 16 February 2026 | 2 weeks. Road closure and diversion between 8pm and 6am. |
| Cambridge | Magdalene Street | 25 March 2026 | 1 week. Road closed with diversion. Pedestrian access allowed. |
| Cambridge | Hauxton Road Roundabout | 1 June 2026 | 2 weeks. Road closure and diversion between 9pm and 5am. Work will take place on all days, including Saturday 6 and Sunday 7 June. |
| Cambridge | East Road | To be confirmed | 2 weeks. Working hours between 6pm and 6am. |
| Cambridge | Gonville Place | To be confirmed | 2 weeks. Working hours between 6pm and 6am. |
| Cambridge | Round Church Street | To be confirmed | 2 weeks. Road closure and diversion between 8pm and 6am. |
| Cambridge | Cherry Hinton Road | To be confirmed | 2 weeks. Road closure and diversion between 8pm and 6am. |
Surface treatment work
We use different types of surface treatments to repair your roads, to learn why please visit our types of road surface treatment page.
2025-2026 programmes
| Parish / Town | Road | Start date | Duration | Type of work |
|---|---|---|---|---|
| Queen Ediths | Godwin Close | 11 April 2025 | Completed | Micro asphalt |
| Queen Ediths | Gunhild Close | 11 April 2025 | Completed | Micro asphalt |
| Queen Ediths | Gunhild Court | 11 April 2025 | Completed | Micro asphalt |
| Queen Ediths | Gunhild Way | 12 April 2025 | Completed | Micro asphalt |
| Queen Ediths | Godwin Way | 13 April 2025 | Completed | Micro asphalt |
| Cherry Hinton | St Thomas's Square | 14 April 2025 | Completed | Micro asphalt |
| Cherry Hinton | St Thomas's Road | 15 April 2025 | Completed | Micro asphalt |
| Coleridge | Suez Road | 15 April 2025 | Completed | Micro asphalt |
| East Chesterton | Evergreens | 16 April 2025 | Completed | Micro asphalt |
| Arbury | Harris Road | 16 April 2025 | Completed | Micro asphalt |
| Arbury | Perse Way | 16 April 2025 | Completed | Micro asphalt |
| Arbury | Durnford Way | 23 April 2025 | Completed | Micro asphalt |
| Arbury | Redfern Close | 23 April 2025 | Completed | Micro asphalt |
| Arbury | Montgomery Close | 24 April 2025 | Completed | Micro asphalt |
| Arbury | Essex Close | 24 April 2025 | Completed | Micro asphalt |
| Arbury | Cunningham Close | 24 April 2025 | Completed | Micro asphalt |
| Arbury | Roland Close | 24 April 2025 | Completed | Micro asphalt |
| Arbury | Wavell Way | 26 April 2025 | Completed | Micro asphalt |
| Arbury | Wynborne Close | 26 April 2025 | Completed | Micro asphalt |
| Arbury | Brimley Road | 26 April 2025 | Completed | Micro asphalt |
| Coleridge | Coleridge Road | 7 May 2025 | Completed | Gripfibre (Micro asphalt) |
| Arbury | Perse Way | 6 October 2025 | Completed | Micro asphalt |
| Kings Hedges | Campkin Road | 21 February 2026 | 4 nights. Road closure between 8pm and 6am | Pre-patching |
2026-2027 programmes
| Parish / Town | Road | Start date | Duration | Type of work |
|---|---|---|---|---|
| Coleridge | Lilac Court | 13 May 2026 | Road closure between 9.30am and 2.30pm | Micro asphalt |
| Coleridge | Coleridge Road | 19 May 2026 | Road closure between 9.30am and 2.30pm | Gripfibre (Micro asphalt) |
Large-scale road maintenance
Our large-scale road maintenance involves reconstruction to replace the top layers of the road and provide a stable support for vehicle movement. Works include, where needed, vegetation clearance, drainage, signage and road markings.
2025-2026 programmes
| Parish / Town | Road | Start date | Duration |
|---|---|---|---|
| Isleham | Prickwillow Road | 6 October 2025 | Completed |
| Little Downham | Hundred Foot Bank | 13 October 2025 | Completed |
| Stuntney | Stuntney Causeway | 15 October 2025 | Completed |
| Ely | Broad Street | 17 October 2025 | Completed |
| Ely | The Gallery | 23 October 2025 | 1 week. Road closure and diversion. Working hours between 9.30am and 2.30pm. |
| Isleham | Mildenhall Road | 31 October 2025 | Completed |
| Littleport | Ponts Hill | 5 November 2025 | Completed |
| Ely | Kings Avenue | 7 November 2025 | Completed |
| Soham | Great Fen Road | 5 December 2025 | 8 weeks. 24hour road closure and diversion. |
| Pymoor | Straight Furlong | 9 March 2026 | 7 weeks. 24hour road closure and diversion. |
Surface treatment work
We use different types of surface treatments to repair your roads, to learn why please visit our types of road surface treatment page.
2025-2026 programmes
| Parish / Town | Road | Start date | Duration | Type of work |
|---|---|---|---|---|
| Little Downham | Kiln Close | 7 April 2025 | Completed | Micro asphalt |
| Little Downham | Orchard Estate | 7 April 2025 | Completed | Micro asphalt |
| Fordham | Murfitts Lane | 9 April 2025 | Completed | Micro asphalt |
| Burrough Green | B1061 Bradley Road | 9 May 2025 | Completed | Gripfibre (Micro asphalt) |
| Chippenham | Snailwell Road | 21 May 2025 | Completed | Surface dressing |
| Ely, Little Thetford | A10 Cambridge Road | 23 May 2025 | Completed | Surface dressing |
| Ely | High Barns | 13 June 2025 | Completed | Gripfibre (Micro asphalt) |
| Stetchworth | Hall Farm | 23 June 2025 | Completed | Emergency resurfacing works |
| Dullingham | Station Road | 21 August 2025 | Completed | Surface dressing |
| Ely, Little Thetford | A10 Cambridge Road | 22 August 2025 | Completed | Surface dressing |
| Wilburton | Pools Road | 26 August 2025 | Completed | Surface dressing |
| Coveney | Main Street | 27 August 2025 | Completed | Surface dressing |
| Ely | High Barns | 8 October 2025 | Completed | Micro asphalt |
| Kirtling | Mill Road | 25 February 2026 | 1 day. Road closure between 8am and 6pm. Monday to Friday only. | Pre-patching |
| Kirtling | Malting End | 25 February 2026 | 1 day. Multi-way traffic lights. Working hours between 8am and 6pm. | Pre-patching |
| Dullingham | London Road | 26 February 2026 |
2 nights. Road closure between 8am and 6pm. |
Pre-patching |
| Kirtling | Newmarket Road | 4 March 2026 | 3 nights. Road closure between 8am and 6pm. Monday to Friday only. | Pre-patching |
| Ashley | B1063 Silverley | 9 March 2026 | 2 days. Road closure and diversion between 9.30am and 3.30pm | Pre-patching |
2026-2027 programmes
| Parish / Town | Road | Start date | Duration | Type of work |
|---|---|---|---|---|
| Kirtling | The Street | 16 April 2026 | 2 days. Road closure and diversion between 8am and 6pm | Pre-patching |
| Cheveley | Moulton Road | 17 April 2026 | 3 days. Road closure and diversion between 8am and 6pm, Monday to Friday only. | Pre-patching |
| Kirtling | Mill Road | 20 April 2026 | 1 day. Road closure and diversion between 8am and 6pm | Surface dressing |
| Newmarket | Ashley Road | 21 April 2026 | 2 days. Road closure and diversion between 9.30am and 2.30pm | Pre-patching |
| Kirtling | Malting End | 21 April 2026 | 1 day. Road closure and diversion between 8am and 6pm | Surface dressing |
| Kirtling | The Street | 21 April 2026 | 1 day. Road closure and diversion between 8am and 6pm | Surface dressing |
| Kirtling | Newmarket Road | 21 April 2026 | 1 day. Road closure and diversion between 8am and 6pm | Surface dressing |
| Littleport | Fishers Bank | 22 April 2026 | 1 day. Road closure between 7.30am and 6pm | Micro asphalt |
| Littleport | The Brambles | 22 April 2026 | 2 days. Road closure between 7.30am and 6pm | Micro asphalt |
| Ashley | B1063 Silverly | 22 April 2026 | 1 day. Road closure and diversion between 9.30am and 3.30pm | Surface dressing |
| Ashley | High Street | 22 April 2026 | 1 day. Road closure and diversion between 9.30am and 3.30pm | Surface dressing |
| Cheveley | Moulton Road | 22 April 2026 | 1 day. Road closure and diversion between 8am and 6pm | Surface dressing |
| Littleport | Sandys Crescent | 23 April 2026 | 1 day. Road closure and diversion between 7.30am and 6pm | Micro asphalt |
| Littleport | Peacock Way | 23 April 2026 | 2 days. Road closure and diversion between 7.30am and 6pm | Micro asphalt |
| Cheveley | Newmarket Road | 23 April 2026 | 1 day. Road closure and diversion between 9.30am and 2.30pm | Surface dressing |
| Newmarket | Ashley Road | 23 April 2026 | 1 day. Road closure and diversion between 9.30am and 2.30pm | Surface dressing |
| Littleport | Anchor Court | 24 April 2026 | 1 day. Road closure and diversion between 7.30am and 6pm | Micro asphalt |
| Dullingham | London Road | 24 April 2026 | 2 days. Road closure and diversion. Working hours Monday to Friday, between 9.30am and 2.30pm. At weekend between 8am and 5pm. | Surface dressing |
| Soham | Centre Road | 25 April 2026 | 2 days. Road closure and diversion between 9.30am and 5.30pm | Micro asphalt |
| Sutton | Sutton Court | 26 April 2026 | 1 day. Road closure between 7.30am and 6pm | Micro asphalt |
Crack sealing
2025-2026 programmes
| Parish / Town | Road | Start date | Duration |
|---|---|---|---|
| Ely | Cam Drive | 26 June 2025 | 5 days. Road closures between 9am and 4pm |
| Soham | The Shade, Townsend, Hall Street | 31 July 2025 | 8 nights. Road closures between 10pm and 6am |
Large-scale road maintenance
Our large-scale road maintenance involves reconstruction to replace the top layers of the road and provide a stable support for vehicle movement. Works include, where needed, vegetation clearance, drainage, signage and road markings.
2025-2026 programmes
| Parish / Town | Road | Start date | Duration |
|---|---|---|---|
| Whittlesey | Eastrea Road | 7 April 2025 | Completed |
| Wisbech | Ramnoth Road | 27 October 2025 | Completed |
| Coates | Coates Road | 12 January 2026 | 2 weeks. Road closure between 8pm and 6am. |
| Chatteris | Sixteen Foot Bank | 2 February 2026 | 8 weeks. 24hour road closure. |
| Leverington | Gorefield Road | 18 February 2026 | 2 weeks. Road closure with diversion between 8am and 5pm. |
| March | City Road | 9 March 2026 | 1 week. Road closure with diversion between 8pm and 6am. |
| Chatteris | Bridge Street | 16 March 2026 | 3 weeks. Road closure with diversion between 8pm and 6am. |
| Chatteris | High Street | 23 March 2026 | 1 week. Road closure with diversion between 8pm and 6am. |
| Wisbech | Ollard Avenue | 30 March 2026 | 3 weeks. Working hours between 8am and 5pm. |
| Wisbech | St Michaels Avenue | 30 March 2026 | 2 weeks. Working hours between 8am and 5pm. |
| Manea | Station Road | 20 April 2026 | 2 weeks. Working hours between 8am and 5pm. |
| March | Creek Road | 5 May 2026 | 2 weeks. Road closure with diversion between 7.30am and 5pm. |
| Wisbech | Norwich Road | 11 May 2026 | 3 weeks. Road closure with diversion between 7pm and 6am. |
| Murrow | Black Drove | To be confirmed | |
| Murrow | Cants Drove | To be confirmed | |
| Doddington | Floods Ferry Road | To be confirmed | |
| Gorefield | Harolds Bank | To be confirmed | |
| Wimblington | Hook Road | To be confirmed | |
| Parson Drove | Silvers Lane | To be confirmed | |
| Manea | Wimblington Road | To be confirmed |
Surface treatment work
We use different types of surface treatments to repair your roads, to learn why please visit our types of road surface treatment page.
2025-2026 programmes
| Parish / Town | Road | Start date | Duration | Type of work |
|---|---|---|---|---|
| Wisbech | Les Baux Place | 1 April 2025 | Completed | Micro asphalt |
| Wisbech | Provence Place | 1 April 2025 | Completed | Micro asphalt |
| Wisbech | Rhone Place | 1 April 2025 | Completed | Micro asphalt |
| Wisbech | Arles Avenue | 1 April 2025 | Completed | Micro asphalt |
| Wisbech | Camargue Place | 2 April 2025 | Completed | Micro asphalt |
| Gorefield | St Marks Road | 2 April 2025 | Completed | Micro asphalt |
| Wimblington | Orchard Way | 3 April 2025 | Completed | Micro asphalt; |
| Wimblington | Fenland Close | 3 April 2025 | Completed | Micro asphalt |
| Wimblington | King Street | 3 April 2025 | Completed | Micro asphalt |
| Whittlesey | Mountbatten Way | 9 April 2025 | Completed | Micro asphalt |
| Whittlesey | Windsor Place | 8 April 2025 | Completed | Micro asphalt |
| Whittlesey | Bellmans Grove | 10 April 2025 | Completed | Micro asphalt |
| Whittlesey | Chestnut Crescent | 10 April 2025 | Completed | Micro asphalt |
| Whittlesey | Hawthorne Drive | 11 April 2025 | Completed | Micro asphalt |
| Whittlesey | Commons Road | 11 April 2025 | Completed | Micro asphalt |
| Tydd St Giles | B1165 Church Lane | 11 May 2025 | Completed | Surface dressing |
| Newton in the Isle | B1165 High Road | 11 May 2025 | Completed | Surface dressing |
| Tipps End | B1100 March Road | 13 May 2025 | Completed | Surface dressing |
| Turves | C71 Burnt House Road | 14 May 2025 | Completed | Surface dressing |
| Whittlesey | St Andrews Place | 8 October 2025 | Completed | Micro asphalt |
| Tydd St Giles | Hockland Road | 4 March 2026 | 1 night. Road closure between 8pm and 6am. | Pre-patching |
2026-2027 programmes
| Parish / Town | Road | Start date | Duration | Type of work |
|---|---|---|---|---|
| Whittlesey | Debdale Court | 1 April 2026 | 1 day. Road closure between 7.30am and 6pm | Micro asphalt |
| Chatteris | Birch Close | 13 April 2026 | 1 day. Road closure between 7.30am and 6pm | Micro asphalt |
| Chatteris | Birch Avenue | 13 April 2026 | 1 day. Road closure between 7.30am and 6pm | Micro asphalt |
| Doddington | Manor Estate | 13 April 2026 | 2 days. Road closure between 9.30am and 2.30pm | Micro asphalt |
| March | Butt Avenue | 14 April 2026 | 1 day. Road closure between 7.30am and 6pm | Micro asphalt |
| March | Brewin Avenue | 14 April 2026 | 2 days. Road closure between 7.30am and 6pm | Micro asphalt |
| March | Birchwood Avenue | 15 April 2026 | 1 day. Road closure between 7.30am and 6pm | Micro asphalt |
| March | Conway Close | 15 April 2026 | 1 day. Road closure between 7.30am and 6pm | Micro asphalt |
| March | Lewis Close | 15 April 2026 | 1 day. Road closure between 7.30am and 6pm | Micro asphalt |
| March | Plowright Close | 15 April 2026 | 2 days. Road closure between 7.30am and 6pm | Micro asphalt |
| Leverington | A1101 Sutton Road | 15 April 2026 | 1 day. Road closure and diversion between 9.30am and 3.30pm | Pre-patching |
| March | Cherrywood Green | 16 April 2026 | 1 day. Road closure between 7.30am and 6pm | Micro asphalt |
| March | Cherrywood Avenue | 16 April 2026 | 1 day. Road closure between 7.30am and 6pm | Micro asphalt |
| March | East Close | 17 April 2026 | 1 day. Road closure between 7.30am and 6pm | Micro asphalt |
| March | Peyton Avenue | 17 April 2026 | 2 days. Road closure between 7.30am and 6pm | Micro asphalt |
| March | West Close | 20 April 2026 | 1 day. Road closure between 7.30am and 6pm | Micro asphalt |
| March | Russell Avenue | 20 April 2026 | 2 days. Road closure between 7.30am and 6pm | Micro asphalt |
| Leverington | A1101 Sutton Road | 30 April 2026 | 1 day. Road closure and diversion between 9.30am and 2.30pm | Surface dressing |
| Tydd St Giles | C10 Hockland Road | 2 June 2026 | 2 days. Road closure and diversion between 9.30am and 2.30pm | Gripfibre (Micro asphalt) |
Crack sealing
2025-2026 programmes
| Parish / Town | Road | Start date | Duration |
|---|---|---|---|
| Wisbech | Mansell Road | 5 June 2025 | 1 day. Road closures between 9am and 4pm |
| Wisbech | Willow Way | 2 June 2025 | 3 days. Road closures between 9am and 4pm |
| Wisbech | Queen Elizabeth Drive | 5 June 2025 | 5 days. Road closures between 9am and 4pm |
| Wisbech | Falklands Drive | 12 June 2025 | 4 days. Road closures between 9am and 4pm |
| Doddington | Newgate Street | 18 June 2025 | 6 days. Road closures between 9am and 4pm |
Large-scale road maintenance
Our large-scale road maintenance involves reconstruction to replace the top layers of the road and provide a stable support for vehicle movement. Works include, where needed, vegetation clearance, drainage, signage and road markings.
2025-2026 programmes
| Parish / Town | Road | Start date | Duration |
|---|---|---|---|
| Holme | New Long Drove | 26 May 2025 | Completed |
| Sawtry | Green End Road | 26 August 2025 | Completed |
| Ramsey Forty Foot | Forty Foot Bank | 12 January 2026 | Completed. Traffic signals in operation. |
| Holme | Long Drove | 25 January 2026 | 9 weeks. 24hour road closure and diversion. |
| Yaxley | Main Street | 26 January 2026 | 1 week. Road closure between 8am and 5pm. |
| Wistow | Mill Road | 2 March 2026 | Completed |
| Buckworth | Barham Road | 5 March 2026 | Completed |
| Hemingford Abbots | Rideaway | 7 March 2026 | 3 weeks. Working hours between 7.30am and 5pm. |
| Godmanchester | Cambridge Road | To be confirmed | |
| The Stukeleys | Spittals Way | To be confirmed |
Surface treatment work
We use different types of surface treatments to repair your roads, to learn why please visit our types of road surface treatment page.
2025-2026 programmes
| Parish / Town | Road | Start date | Duration | Type of work |
|---|---|---|---|---|
| Buckden | The Oslers | 1 April 2025 | Completed | Micro asphalt |
| Buckden | Springfield Close | 1 April 2025 | Completed | Micro asphalt |
| Hemingford Grey | The Rampleys | 2 April 2025 | Completed | Micro asphalt |
| Yaxley | Laburnum Avenue | 12 April 2025 | Completed | Micro asphalt |
| Huntingdon | Maryland Avenue | 14 April 2025 | Completed | Micro asphalt |
| Stilton | Church Street | 11 May 2025 | Completed | Gripfibre (Micro asphalt) |
| Folksworth | Washingley Lane | 15 May 2025 | Completed | Gripfibre (Micro asphalt) |
| Hartford | A141 Huntingdon Northern Bypass | 29 May 2025 | Completed | Surface dressing |
| Wood Walton | B1090 Walton Hill | 29 May 2025 | Completed | Surface dressing |
| Great GIdding | Main Street | 31 May 2025 | Completed | Surface dressing |
| Fenstanton | A1096 London Road | 1 June 2025 | Completed | Surface dressing |
| Yaxley | Dovecote Lane | 2 June 2025 | Completed | Gripfibre (Micro asphalt) |
| Yaxley | Church Street | 3 June 2025 | Completed | Gripfibre (Micro asphalt) |
| Yaxley | Main Street | 4 June 2025 | Completed | Gripfibre (Micro asphalt) |
| Elton | Bullock Road | 27 August 2025 | Completed | Surface dressing |
| Godmanchester | Porch Close | 7 October 2025 | Completed | Micro asphalt |
| Yaxley | Main Street (Between Middleton Road and Church Street) | 3 November 2025 |
Completed |
Gripfibre Micro asphalt (Ironwork adjustments) |
| Kings Ripton | Sapley Road | 27 February 2026 | 2 days. Road closure between 8am and 6pm | Pre-patching |
2026-2027 programmes
| Parish / Town | Road | Start date | Duration | Type of work |
|---|---|---|---|---|
| Farcet | Southoe Road | 1 April 2026 | 1 day. Road closure between 9.30am and 2.30pm | Micro asphalt |
| Farcet | St Marys Street | 1 April 2026 | 3 days. Road closure and diversion between 9.30am and 2.30pm | Micro asphalt |
| Stilton | Turpins Ride | 7 April 2026 | 1 day. Road closure between 7.30am and 6pm | Micro asphalt |
| Stilton | Ermine Crescent | 7 April 2026 | 1 day. Road closure between 7.30am and 6pm | Micro asphalt |
| Stilton | Talbot Close | 7 April 2026 | 2 days. Road closure between 7.30am and 6pm | Micro asphalt |
| Stilton | George Street | 8 April 2026 | 1 day. Road closure between 7.30am and 6pm | Micro asphalt |
| Stilton | Ash Road | 8 April 2026 | 1 day. Road closure between 7.30am and 6pm | Micro asphalt |
| Stilton | Elm Close | 8 April 2026 | 2 days. Road closure between 7.30am and 6pm | Micro asphalt |
| Folksworth | Chervil Close | 9 April 2026 | 1 day. Road closure between 7.30am and 6pm | Micro asphalt |
| Folksworth | Mallow Lane | 9 April 2026 | 1 day. Road closure between 7.30am and 6pm | Micro asphalt |
| Folksworth | Hawthorn Road | 9 April 2026 | 2 days. Road closure between 7.30am and 6pm | Micro asphalt |
| Folksworth | Blackmans Road | 10 April 2026 | 1 day. Road closure between 7.30am and 6pm | Micro asphalt |
| Folksworth | Townsend Way | 10 April 2026 | 1 day. Road closure and diversion between 7.30am and 6pm | Micro asphalt |
| Folksworth | Castel Way | 10 April 2026 | 2 days. Road closure between 9.30am and 2.30pm | Micro asphalt |
| Ramsey | Lawrence Road | 11 April 2026 | 1 day. Road closure between 7.30am and 6pm | Micro asphalt |
| Ramsey | Oates Way | 11 April 2026 | 1 day. Road closure between 7.30am and 6pm | Micro asphalt |
| Ramsey | Abbots fields | 11 April 2026 | 2 days. Road closure between 7.30am and 6pm | Micro asphalt |
| Ramsey | Abbots Close | 12 April 2026 | 1 day. Road closure between 7.30am and 6pm | Micro asphalt |
| Warboys | First Avenue | 12 April 2026 | 1 day. Road closure between 9.30am and 2.30pm | Micro asphalt |
| Warboys | Second Avenue | 12 April 2026 | 1 day. Road closure between 9.30am and 2.30pm | Micro asphalt |
| Warboys | Third Avenue | 12 April 2026 | 1 day. Road closure between 9.30am and 2.30pm | Micro asphalt |
| Earith | St Marys | 26 April 2026 | 2 days. Road closure between 7.30am and 6pm | Micro asphalt |
| Colne | The Rhees | 27 April 2026 | 1 day. Road closure between 7.30am and 6pm | Micro asphalt |
| Bluntisham | Presses Close | 27 April 2026 | 1 day. Road closure between 9.30am and 2.30pm | Micro asphalt |
| St Ives | Virginia Way | 27 April 2026 | 2 days. Road closure between 9.30am and 2.30pm | Micro asphalt |
| St Ives | Michigan Road | 28 April 2026 | 1 day. Road closure between 9.30am and 2.30pm | Micro asphalt |
| St Ives | Alabama Way | 28 April 2026 | 1 day. Road closure between 9.30am and 2.30pm | Micro asphalt |
| St Ives | California Road | 28 April 2026 | 2 days. Road closure between 9.30am and 2.30pm | Micro asphalt |
| Hartford | Eaton Close | 29 April 2026 | 1 day. Road closure between 7.30am and 6pm | Micro asphalt |
| Hartford | Mill Road | 29 April 2026 | 2 days. Road closure and diversion between 7.30am and 6pm | Micro asphalt |
| Hartford | Lark Crescent | 30 April 2026 | 1 day. Road closure between 7.30am and 6pm | Micro asphalt |
| Hartford | Arundel Road | 30 April 2026 | 1 day. Road closure and diversion between 7.30am and 6pm | Micro asphalt |
| Kimbolton | Station Road | 30 April 2026 | 1 day. Road closure between 9.30am and 3.30pm | Surface dressing |
| Houghton | Thicket Road | 30 April 2026 | 1 day. Road closure between 9.30am and 2.30pm | Surface dressing |
| Godmanchester | The Close | 1 May 2026 | 1 day. Road closure between 7.30am and 6pm | Micro asphalt |
| Godmanchester | Fairey Avenue | 5 May 2026 | 1 day. Road closure between 7.30am and 6pm | Micro asphalt |
| Godmanchester | Stuart Close | 5 May 2026 | 1 day. Road closure between 7.30am and 6pm | Micro asphalt |
| Godmanchester | Ravenshoe | 5 May 2026 | 2 days. Road closure between 7.30am and 6pm | Micro asphalt |
| Godmanchester | Petit Way | 6 May 2026 | 1 day. Road closure and diversion between 7.30am and 6pm | Micro asphalt |
| Godmanchester | Windsor Road | 6 May 2026 | 1 day. Road closure and diversion between 7.30am and 6pm | Micro asphalt |
| Godmanchester | Lions Cross | 6 May 2026 | 2 days. Road closure between 7.30am and 6pm | Micro asphalt |
| Hilton | Scotts Close | 7 May 2026 | 1 day. Road closure between 7.30am and 6pm | Micro asphalt |
| Hilton | Scotts Crescent | 7 May 2026 | 2 days. Road closure between 7.30am and 6pm | Micro asphalt |
| Eynesbury | Caernarvon Road | 8 May 2026 | 2 days. Road closure and diversion between 9.30am and 2.30pm | Micro asphalt |
| Eynesbury | Ridgeway | 9 May 2026 | 1 day. Road closure and diversion between 9.30am and 2.30pm | Micro asphalt |
| Eynesbury | Edward Road | 9 May 2026 | 2 days. Road closure and diversion between 9.30am and 2.30pm | Micro asphalt |
| Eynesbury | Bishops Road | 10 May 2026 | 1 day. Road closure and diversion between 9.30am and 2.30pm | Micro asphalt |
| Huntingdon | Coneygear Road | 26 May 2026 | 3 days. Road closure and diversion between 9.30am and 2.30pm | Gripfibre (Micro asphalt) |
| Sapley | Kings Ripton Road | 28 May 2026 | 3 days. Road closure and diversion between 9.30am and 2.30pm | Gripfibre (Micro asphalt) |
| Kings Ripton | Sapley Road | 30 May 2026 | 3 days. Road closure and diversion between 9.30am and 2.30pm | Gripfibre (Micro asphalt) |
| Huntingdon | Mayfield Road | 1 June 2026 | 2 days. Road closure and diversion between 9.30am and 2.30pm | Gripfibre (Micro asphalt) |
Crack sealing
2025-2026 programmes
| Parish / Town | Road | Start date | Duration |
|---|---|---|---|
| St Ives | Burleigh Drive | 3 July 2025 | 3 days. Road closures between 9am and 4pm |
| St Ives | Edinburgh Drive | 8 July 2025 | 2 days. Road closures between 9am and 4pm |
| St Ives | Green Leys/Paragon Road | 10 July 2025 | 7 days. Road closures between 9am and 4pm |
| St Ives | High Leys | 21 July 2025 | 4 days. Road closures between 9am and 4pm |
| Wyton-on-the-Hill | St Ives Road A141 | 28 July 2025 | 3 nights. Road closures between 10pm and 6am |
Large-scale road maintenance
Our large-scale road maintenance involves reconstruction to replace the top layers of the road and provide a stable support for vehicle movement. Works include, where needed, vegetation clearance, drainage, signage and road markings.
2025-2026 programmes
| Parish / Town | Road | Start date | Duration |
|---|---|---|---|
|
Harston |
London Road |
6 January 2026 |
Completed |
|
Shudy Camps |
Main Street |
14 January 2026 |
Completed |
|
Graveley |
High Street |
20 January 2026 |
Completed |
|
Willingham |
Earith Road |
2 February 2026 |
3 weeks. Road closure between 8am and 5pm. |
|
Cambourne |
Cambourne Road |
9 February 2026 |
1 week. Road closure and diversion between 9pm and 5am. |
|
Waterbeach |
Clayhithe Road |
23 February 2026 |
1 week. Road closure and diversion between 10pm and 6am. |
|
Great Shelford |
Granham's Road |
25 February 2026 |
3 days. Road closure and diversion between 7.30am and 6pm on Wednesday 25 and Thursday 26 February. Road closure and diversion between 8pm and 5am on Sunday 1 March through to Monday 2 March. |
| Great Shelford | Tunwells Lane | 7 April 2026 | 4 weeks. Road closure and diversion between 8pm and 6am. |
| Pampisford | Causeway | 8 June 2026 | 3 weeks. Road closure and diversion between 8.30pm and 5.30am. |
|
Cottenham |
High Street |
To be confirmed |
To be confirmed |
Surface treatment work
We use different types of surface treatments to repair your roads, to learn why please visit our types of road surface treatment page.
2025-2026 programmes
| Parish / Town | Road | Start date | Duration | Type of work |
|---|---|---|---|---|
| Histon | Melvin Way | 2 April 2025 | Completed | Micro asphalt |
| Waterbeach | Payton Way | 3 April 2025 | Completed | Micro asphalt |
| Waterbeach | Spurgeons Way | 7 April 2025 | Completed | Micro asphalt |
| Waterbeach | Providence Way | 8 April 2025 | Completed | Micro asphalt |
| Barton | Kings Grove | 9 April 2025 | Completed | Micro asphalt |
| Weston Green | Horseshoes Lane | 10 April 2025 | Completed | Micro asphalt |
| Fulbourn | St Vigors Road | 10 April 2025 | Completed | Micro asphalt |
| Fulbourn | All Saints Road | 10 April 2025 | Completed | Micro asphalt |
| Teversham | Fulbourn Old Drift | 10 April 2025 | Completed | Micro asphalt |
| Over | Glover Street | 6 May 2025 | Completed | Gripfibre (Micro asphalt) |
| Little Chishill | Little Chishill Road | 17 May 2025 | Completed | Surface dressing |
| Great Chishill | May Street | 17 May 2025 | Completed | Surface dressing |
| Litlington | Royston Road | 18 May 2025 | Completed | Surface dressing |
| Steeple Morden | Cheyney Street | 18 May 2025 | Completed | Surface dressing |
| West Wratting | B1052 Bull Lane | 18 May 2025 | Completed | Surface dressing |
| Thriplow | Gravel Pit Hill | 19 May 2025 | Completed | Surface dressing |
| Horseheath | Horseheath Green | 19 May 2025 | Completed | Surface dressing |
| Fulbourn | Teversham Road | 20 May 2025 | Completed | Surface dressing |
| Carlton | Brinkley Road | 21 May 2025 | Completed | Surface dressing |
| Over | Gravel Bridge Road | 27 May 2025 | Completed | Gripfibre (Micro asphalt) |
| Oakington | Dry Drayton Road | 9 June 2025 | Completed | Gripfibre (Micro asphalt) |
| Fulbourn | Apthorpe Street / Cow Lane | 10 June 2025 | Completed | Gripfibre (Micro asphalt) |
| Fulbourn | St Vigors | 6 October 2025 | Completed | Micro asphalt |
| Meldreth | Station Road | 2 March 2026 | 2 days. Road closure and diversion between 9.30am and 2.30pm | Pre-patching |
| Fulbourn | Teversham Road | 9 March 2026 | 2 days. Road closure and diversion between 9.30am and 2.30pm | Pre-patching |
2026-2027 programmes
| Parish / Town | Road | Start date | Duration | Type of work |
|---|---|---|---|---|
| Newton | Colville Road | 21 April 2026 | 2 days. Road closure between 7.30am and 6pm | Micro asphalt |
| Fulbourn | Cambridge Road | 22 April 2026 | 3 nights. Road closure and diversion between 8pm and 6am | Pre-patching |
| Fulbourn | Cambridge Road | 26 April 2026 | 1 day. Road closure and diversion between 8am and 5pm | Surface dressing |
| Fulbourn | Teversham Road | 27 April 2026 | 1 day. Road closure and diversion between 8am and 6pm | Surface dressing |
| Fulbourn | B1368 London Road | 27 April 2026 | 1 day. Road closure and diversion between 9.30am and 2.30pm | Surface dressing |
| Meldreth | Kneesworth Road | 28 April 2026 | 1 day. Road closure and diversion between 8am and 6pm | Surface dressing |
| Toft | B1046 High Street | 29 April 2026 | 1 day. Road closure and diversion between 9.30am and 2.30pm | Surface dressing |
| Toft | Comberton Road | 29 April 2026 | 1 day. Road closure and diversion between 9.30am and 2.30pm | Surface dressing |
| Melbourn | Clear Crescent | 10 May 2026 | 2 days. Road closure and diversion between 7.30am and 6pm | Micro asphalt |
| Haslingfield | Scotts Yard | 11 May 2026 | 1 day. Road closure between 7.30am and 6pm | Micro asphalt |
| Haslingfield | Fountain Lane | 11 May 2026 | 2 days. Road closure and diversion between 7.30am and 6pm | Micro asphalt |
| Sawston | Hall Crescent | 12 May 2026 | 1 day. Road closure between 7.30am and 6pm | Micro asphalt |
| Sawston | Huddleston Way | 12 May 2026 | 1 day. Road closure between 7.30am and 6pm | Micro asphalt |
| Sawston | St Marys Road | 12 May 2026 | 2 days. Road closure between 7.30am and 6pm | Micro asphalt |
| Waterbeach | Coronation Close | 13 May 2026 | 2 days. Road closure between 7.30am and 6pm | Micro asphalt |
| Meldreth | Station Road | 18 May 2026 | 2 days. Road closure and diversion between 9.30am and 2.30pm | Gripfibre (Micro asphalt) |
Crack sealing
2025-2026 programmes
| Parish / Town | Road | Start date | Duration |
|---|---|---|---|
| Histon | Station Road | To be confirmed | |
| Impington | Cambridge Road | To be confirmed |
Roadwork and traffic information
Our interactive map gives you more detail on the latest roadworks, road closures and diversions. Works listed on this page are included.
Visit our road and traffic information page to access the map and instructions on how to use. Details of upcoming roadworks in PDF format are also provided.
The map uses data from Causeway one.network. Enter your road name and see the types of work happening today or in the next two weeks, three or twelve months.
You can also follow us on X (formerly Twitter) for updates on where we are working - @Cambs_Traffic
Can't find what you are looking for?
If you are unable to find a scheme on this page, it may be part of our reactive or cyclical maintenance programmes.
These works are more area based and include gully cleansing, road patching and public rights of way maintenance.
FAQ
Please read through our frequently asked questions. If you are unable to find the answer please contact us.
The work area is the section of the road where our operatives will be working. The road closure area often extends beyond this to manage through traffic and divert it on to an alternative route. This helps us do the work quickly and efficiently, while keeping residents, road users and the workforce safe. 
If you receive information notifying you about a road closure, we will include a map which indicates both the work and road closure areas if these are different.
As the work involves heavy plant and equipment, we cannot guarantee you will be able to access your property without having to wait or access via the other end of the works.
If you normally drive into or out of the work area during the hours when the closure is in place, we may ask you to please make alternative arrangements.
We will often phase works to try to reduce the disruption this can cause, and the site team will be available to communicate with residents and businesses regarding this.
We will always maintain access to properties if it is safe to do so. Delays will sometimes be unavoidable when we must move machinery or equipment out of the way. We thank you for your patience and cooperation while this is done.
Work is phased to allow property access from at least one end of the road. Access may differ, depending on where we are working.
We place advance warning signs at the starting points of our works at least 14 days before the work starts.
We will inform residents and businesses which are located with the area of work, via letter or leaflet drop, at least 14 days in advance of work starting, wherever possible.
We try to keep noise to a minimum, and plan noisier working activities for earlier on in shifts where we are working at night in residential areas. However, the work is being delivered using heavy plant and machinery and this will cause noise and disruption whilst the work is on site, especially where we are working overnight. To try to limit this we:
- Consider alternative ways of working, for example during the day, instead of night, when working in residential areas at the weekend.
- Working reduced hours overnight. This approach often means a longer delivery programme, whereas working longer shifts will result in the work being completed quicker.
- Working during the day whenever we can to reduce costs and disruption to residents during unsociable hours.
Provided your speed is under 20mph, you can use a treated road approximately 20 minutes after a treatment product has been applied.
Please take care when using a newly laid road surface as some loose chippings are likely.
Please follow any temporary speed limits in place.
We can only lay road surface treatments in good weather. If the ground is still wet, it is raining, too hot or too cold for the surface treatment to be effective, we must postpone works until the weather conditions improve. This is to ensure the work is long-lasting and successful.
The schedule on this page is updated regularly to reflect any changes.
When choosing a route to use for diverted traffic, we use the same category or a higher category road as the temporarily closed road. This is to ensure the diversion route can cope with the same type of traffic as the temporarily closed road.
In certain rural locations, if there is no suitable alternative, we may have to divert using a lower category route. Please note that we only signpost approved diversion routes.
Sometimes, road users may choose to use an alternative local road. We do not have the powers to prevent highway users from using these alternative routes.
Contact
To report an issue with a road, please visit our report a highways fault page.
If you have any queries or require any additional information please complete our make an enquiry online form.
Capital maintenance programme
For more information on the workstreams covered please visit our capital maintenance programme page.
How we are improving highways maintenance
Over the past two years, we have made the biggest investment in the highways network in over a decade, and it is important to show you where your money is spent.
Visit how we are improving highways maintenance. This page outlines our priorities, what improvements were made in 2024/25, and funding allocation for 2025/26.